2017/3/2(Fri.) * Remote participants by eZuce: None * Report of work (*:responsible person) * Alignment: Enomoto, Miyo, Yokozawa * IMC and IMMT was aligned to center PRs. * Beam spot was not seen at the end. * We absolutely need monitors to check beam position at all the mirrors. * IOO: kokeyama * Alignment to MC was fixe. * AOS: * Lasers of oplev will can be dying soon. * The lifetime is about 100000h. * CRY: mirror temperature 89K. * Work plan (*:responsible person) * Alignment: * Alignment to IYA, or IYC will be checked and we will find the spot at the end then. * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. * Weekly * Week of 2/26 * ETMY tuninng. * Beam alignment to REFL port. * week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber * week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Issues