Line 3: Line 3:
 * Remote participants by eZuce: None  * Remote participants by eZuce: Kimura

2017/3/6(Tue.)

  • Remote participants by eZuce: Kimura
  • Report of work (*:responsible person)
    • Alignment: Enomoto
      • Beam was found again at PD and Tcam of ETMX and Tcam of ETMY. Baffle PD at
    • BS: Mark
      • We lifted up the optical table.
    • IOO:
      • IMMT2 cannot be seen by camera. We will work on camera this week.
    • CRY: mirror temperature 71K.
  • Work plan (*:responsible person)
    • Alignment: Enomoto
      • We will find beam at the ETMY or ETMX by dithering PR3.
    • AOS: Akutsu, Michimura
      • Items PR2 chamber will be replaced, and green light will be used in the afternoon.
      • WAB work at the IYA.
  • Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end for both IR and green.
  • Weekly
    • week of 3/5
      • IYC door will be closed.
      • Exchanging items and cleaning inside the PR2 chamber
    • week of 3/12
      • TMS installation at ETMY.
      • Connecting ducts at the corner area.
    • week of 3/19
      • Vacuum test at at the corner area.
      • TMS alignment using green light at ETMY.
      • Beam alignment to REFL port.
  • Issues

KAGRA/Commissioning/DailyWork/2018-03-06 (last edited 2018-03-07 08:55:41 by OsamuMiyakawa)