=== 2018/4/9(Mon.) === * Remote participants by eZuce: ==== Report of work (*:responsible person) ==== * IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto * Light from ETMY was seen at the REFL. No light was confirmed from ETMX due to the work at ETMX. * Connection between k1lsc and k1bs was done. * DAQ: *Miyakawa * Minute raw date is being shifted to k1tw0. k1fw0 currently writing full and science and minute data seems to be working very well. ==== Work plan (*:responsible person) ==== * Alignment: Enomoto * Alignment to ETMX will be verified Tuesday evening. * Vacuum: Kimura * Disassembling outer frames today * Closing will be done tomorrow. * Installation of Illuminator and viewport are still remaining. It will be done today. * Laser will be stopped day time during this week. ==== Laser hazard ==== * [AM] * IR: PSL, Yend 1F * Green: off * [PM] * IR: PSL, Yend 1F * Green: off * [night] * IR: PSL, Yend 1F * Green: off ==== Weekly ==== * week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC ==== Issues ====