=== Daily meeting === * Date and time: Every weekday, 1PM * ~10min, as short as possible * Location: Control room and Fan hut connected by eZuce === 2018/8/31(Fri.) === * PSL for high-power laser will finish by 8/31 and they provides the high power laser to the interferometer. * Out put of PSL will be few Watts. * Safety for the high power laser should be announced. * Actual night work will start 9/3 (9/1, 9/2 are weekends). * We will have a daily meeting on 9/3 that is the first day of night work managed by Izumi. * Furuta-san will attend this meeting every day to tell the laser hazard for Engineers. * One Car (Serena) will be assigned to commissioning work. ==== Attendance ==== * Control room: Miyakawa, Tomura, Miyamoto * Fan hut: Furuta * educe: ==== Laser hazard ==== |||| ||Before 3PM ||After 3PM || |||| || |||| ||Center||upstream IMM||IR ||IR || || ||PSL ||IR & Green||IR & Green|| ||||X end 1F ||IR ||IR || ||||Y end 1F ||N/A ||N/A || ---- ==== Transition from morning work (*:responsible person) ==== * Alignment of IFI dose not point center of IMMT1. It goes to 1.5cm right of IMMT1. It seems to have no clip at IMMT1. * We should discuss that we move IMMT1. ==== Report of work (*:responsible person) ==== * EX camera anad illuminator are recovered. ==== Work plan (*:responsible person) ====