=== 2018/9/1(Mon.) === * Beam will be injected into IFO at 3PM. Injecting power into IFO will be few Watts. * Safety for the high power laser should be announced through this meeting. * Furuta-san will attend this meeting every day to tell the laser hazard for Engineers. * Actual night work will start today. * One Car (Serena) will be assigned to commissioning work. ==== Attendance ==== * Control room: * Fan hut: Furuta * educe: ==== Laser hazard ==== |||| ||Before 3PM ||After 3PM || |||| || |||| ||Center||upstream IMM||IR ||IR || || ||PSL ||IR & Green||IR & Green|| ||||X end 1F ||IR ||IR || ||||Y end 1F ||N/A ||N/A || ---- ==== Transition from morning work (*:responsible person) ==== ==== Report of work (*:responsible person) ==== ==== Work plan (*:responsible person) ==== * IMMT1 will move 1.5cm to the right direction to have a beam on the center.