=== 2019/3/11(Mon.) === === Schedule === * Center * --(2/26-27: Venting)-- * 2/28-3/15: Health check and maintenance for VIS * --(PRM: One flag was dropped. -> leave it)-- * --(3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.)-- * 3/4-8 PRM: Misalignment does not reach where beam hits damper. * ~3/15 BS: Yaw offset adjustment by hand. -> 3/5-6 * --(3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.)-- * 3/18-19: Re-alignment * 3/19: Closing * 3/20: pump down * Yend * --(1/25-2/20: Yend Pcal finalization)-- * --(3/5: EYA remaining works by Enomoto, Inoue.)-- * --(2/25-3/5: Yend WAB finalization)-- * --(3/6: Y end closing (no laser hazard at least in the morning))-- * --(3/7: Y end pump down)-- * --(3/7,8: leak test)-- * Xend * --(2/11-2/14: Xend NAB installation)-- * --(2/21: Removing FC, Payload release)-- * --(2/27: ETMX release)-- * --(2/23-3/6: Xend Pcal finalization 1)-- * --(Periscope installation)-- * --(3/6: Beam position by IR and Green)-- * --(3/5 AOS: EY and EX(if they have time) work.)-- * --(3/6: Green X alignment (no IR), and no hazard at Y end.)-- * 3/11, 18,19: Xend WAB finalization. * 3/11~3/15: ETMX tuning. * 3/19: Heatlink etc. * 3/19: ETMX finalization by Takahashi * 3/18,19: ETMX alignement * 3/21 closing * 3/22 Pumping down * Leak test * 3/18~ : Night work starts, daily meeting will be moved to 1PM * Summary of work will last for a while in the morning meeting. * 2/18-2/22: PRMI commissioning * 3/25~?: DRMI commissioning * 3/25-4/19: Y arm commissioning * 3/25-4/19: FPMI commissioning ==== Note ==== * Night work does not start from 3/11 due to the 2weeks delay by VIS troubles. * It does not mean that night work is prohibited but it means that officially night shift responsible person won't be assigned and we have no daily meeting at 1pm. * Official night work starts 3/18 or 3/25, but not determined yet. === Weekend === ==== Report of work ==== * Type Bp: health check PR3 seems to be OK. * Type B: SR2 and SR3 SRM are fine. SRM had glitch. * IM drift seem to be zero and opposite direction. * Type A: F3 of ETMY seems to be stuck somehow, by that temperature changed or vacuum started? * Temperature is low under 20degree at 1st floor of ETMY. * PEM: finished work at ETMX area. ==== Work plan ==== * AOS: Finalization of WAB at ETMX will start today. It lasts this week.