=== 2019/4/5(Fri.) === ==== Schedule ==== * Center * --(3/25: Venting)-- * 3/27-4/10: Fixing PR2 * 4/4 -4/5: Gluing * 4/12: Closing and pump down * ITMX: * --(3/19: Cooling stop)-- * --(3/25: Venting start)-- * --(3/27: Opning chamber)-- * --(3/27~: Fixing thermal touch)-- * --(4/2~: closing chamber and start pumping down.)-- * 4/12: Cooling starts. * Xend * --(3/25: closing and pump down)-- * 4/11: Cooling start * Yend * --(3/26: Venting start)-- * --(3/28~: Fixing short inside chamber)-- * --(4/3: Fixing F0 actuator)-- * --(4/4~: closing chamber and start pumping down.)-- * 4/9: Cooling starts. * 4/8~ or 4/15~ : Night work starts, daily meeting will be moved to 1PM * Summary of work will last for a while in the morning meeting. * April: Measurement of TF, payload diagonalization on ITMX * End of April~: DRMI commissioning * End of April~: Y arm commissioning * ~End of May: FPMI commissioning ==== Note ==== * Official night work starts 4/8 or 4/15. ==== Weekend ==== * Saturday and Sunday will be on laser hazard all the area. * Sat., Sun.: iMC alignment (Kokeyama) * Sat.: ETMX (Lucia) * Sat.: ETMY (Suzuki) ==== Report of work ==== * Type Bp: Total 3 flags were glued on PR2 and PRM. Jigs will be released today. * CRY: It was found that on of the PD sensor at ETMX cryostat has no output. Now Ushiba-kun is checking it. * PEM, VAC: Vacuum values of center area have been added to monitor by Yokozawa-kun. * VIS: All VIS will be finally checked today and next week. ==== Work plan ====