Line 30: Line 30:
  * 4/22: Leak check   * 4/16~4/22: Leak check

2019/4/16(Tue.)

Schedule

  • Center
    • 3/25: Venting

    • 3/27-4/9: Fixing PR2 or others

      • 4/4 -4/5: Gluing

      • 4/8: alignment check

      • 4/8-10: OSEM adjustment

    • 4/10: alignment check

    • 4/11: VIS final health check

    • 4/11-12: Closing

    • 4/12: Pump down

    • 4/29,30: Leak check
  • ITMX:
    • 3/19: Cooling stop

    • 3/25: Venting start

    • 3/27: Opning chamber

    • 3/27~: Fixing thermal touch

    • 4/2~: closing chamber and start pumping down

    • 4/10: Cooling starts.

  • Xend
    • 3/25: closing and pump down

    • 4/8: Leak check

    • 4/9-10: venting

    • 4/11: Exchange a broken LED for Photo sensor

    • 4/12: closing chamber and start pumping down

    • 4/16~4/22: Leak check
    • 4/22: Cooling start
  • Yend
    • 3/26: Venting start

    • 3/28~: Fixing short inside chamber

    • 4/3: Fixing F0 actuator

    • 4/4~: closing chamber and start pumping down.

    • 4/10: Cooling starts.

  • April: Measurement of TF, payload diagonalization on ITMX
  • End of April~: DRMI commissioning
  • End of April~: Y arm commissioning
  • ~End of May: FPMI commissioning

Note

  • Commissioning meeting moves at 1PM from this week.

Night work

  • Alignment (Nakano, Enomoto, Sugimoto)

Weekend

Report of work

  • Type B: BS SR2 are healthy. SRM was touching but it was lifted. It seems to be OK.
    • SRM and SR3 needs to be lifted up.
  • Type A: ETMX is healthy.
    • Payload status will be checked.
  • Type A: ITMY payload TF was measured by high power coil driver. Coupling was much.
  • Type Bp: PR3 seems to be healthy. Others will be checked.
  • IOO: FSS was recovered.
  • IOO: iMC ASC is going on.
  • MIF: Alignment recovery will be performed today.
  • PEM: ETMX characterization started. Microphone, Magnet meter.
  • PEM: AC100V at ETMX was very dirty. It is not sine wave at all.

Work plan