Line 41: Line 41:

 * VAC: In the central area, leaks were found and it was fixed. Pumping down started again.
  * Height of ITMX and ITMY will be measured by Suzuki-san.

2019/5/7(Tue.)

Schedule

  • Center
    • 4/12: Pump down

    • 4/29,30: Leak check

    • 5/2: Vent and pumpdown
    • 5/9: leak check
  • ITMX:
    • 4/10: Cooling starts.

  • Xend
    • 4/25: Pumpdown

    • 5/2: leak check

    • 5/2: Cooling start

  • Yend
    • 4/4~: closing chamber and start pumping down.

    • 4/10: Cooling starts.

  • April: Measurement of TF, payload diagonalization on ITMX
  • End of April~: DRMI commissioning
  • End of April~: Y arm commissioning
  • ~End of May: FPMI commissioning

Note

Night work

  • Y arm commissioning, from the control room.

Weekend

Report of work

  • IR laser frequency was too noisy for mass feedback lock.
    • Frequency is stabilized by X arm cavity, and Y arm will be locked to stabilized laser.
  • Beam spot on ITMY was too high.
    • Needs BS camera.
    • Height of ITMX and ITMY will be measured by Suzuki-san.

Work plan

KAGRA/Commissioning/DailyWork/2019-05-07 (last edited 2019-05-07 13:03:50 by OsamuMiyakawa)