=== 2019/5/7(Tue.) === ==== Schedule ==== * Center * --(4/12: Pump down)-- * --(4/29,30: Leak check)-- * 5/2: Vent and pumpdown * 5/9: leak check * ITMX: * --(4/10: Cooling starts.)-- * Xend * --(4/25: Pumpdown)-- * --(5/2: leak check)-- * --(5/2: Cooling start)-- * Yend * --(4/4~: closing chamber and start pumping down.)-- * --(4/10: Cooling starts.)-- * April: Measurement of TF, payload diagonalization on ITMX * End of April~: DRMI commissioning * End of April~: Y arm commissioning * ~End of May: FPMI commissioning ==== Note ==== * ==== Night work ==== * Y arm commissioning, from the control room. ==== Weekend ==== ==== Report of work ==== * IR laser frequency was too noisy for mass feedback lock. * Frequency is stabilized by X arm cavity, and Y arm will be locked to stabilized laser. * Beam spot on ITMY was too high. * Needs BS camera. * Height of ITMX and ITMY will be measured by Suzuki-san. ==== Work plan ====