=== 2019/5/8(Wed.) === ==== Schedule ==== * Center * --(4/12: Pump down)-- * --(4/29,30: Leak check)-- * ~5/3: Vent and pumpdown * 5/9: leak check * ITMX: * --(4/2~: closing chamber and start pumping down.)-- * --(4/10: Cooling starts.)-- * 5/8: Cooling done * Xend * --(4/25: Pumpdown)-- * --(5/2: leak check)-- * --(5/2: Cooling start)-- * Yend * --(4/4~: closing chamber and start pumping down.)-- * --(4/10: Cooling starts.)-- * 5/8: Cooling done * April: Measurement of TF, payload diagonalization on ITMX * End of April~: DRMI commissioning * End of April~: Y arm commissioning * ~End of May: FPMI commissioning ==== Note ==== * ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * Hight measurement of ITMX and ITMY was done. The result was +5mm and -5mm, and they are consistent. ==== Work plan ==== * PEM: Calibration of Magneto meter * COM: vTrial of Yarm lock with X arm lock. All air controller will be off from 3PM.