=== 2019/5/20(Mon.) === ==== Schedule ==== * 5/14: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS, ) * 5/17~ increasing ETMY temperature. * 5/20-24: Exchanging cryo valves. * Center * ITMX: * Xend * --(5/2: Cooling start)-- * 5/29: Cooling done * Yend * End of April~: Y arm commissioning * ~End of May: Y arm and FPMI commissioning ==== Note ==== * ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * Dew was found at ITMY, ETMY and ETMX. * COM: Finnesse was ~28 on Thursday. * Friday, after increasing temperature, finesse increased to ~120 with 30K. * Sunday, temperature increased to 50K and the finesse was 140, not drastic improvement. * PRM will turn off COACH filter on PSL for 10 min to measure acoustic back ground. * Type B: To improve Shield for SR2 oplev * Only ETMY temperature is increasing. * DAQ is not stable. All connection was lost yesterday and this morning. ==== Work plan ==== * IOO: It takes some time for checking MZ this morning, or afternoon if needed. * Position of ITMX using auto leveler this afternoon or tomorrow depending work of MZ above. * CRY: Exchanging cryo valve during this week.