=== 2019/6/10(Mon.) === ==== Schedule ==== * --(5/22-23: MZ release from PSL)-- * --(5/20-24: Exchanging cryo valves.)-- * --(5/27-6/2: Y arm mass lock.)-- (not done yet) * --(5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS) )-- * 6/3-6/14: Installation of TMS for ETMY * 6/8: Engineering run * ITMX * --(5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm)-- * --(5/22AM~: tuned off shield cooler, finesse measurement for Xarm)-- * ETMX * --(5/2: Cooling start)-- * ITMY * --(5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm)-- * ETMY * --(5/17~: tuned off ETMY cryostat cooler)-- * Long term: * 4/22-5/31: Yarm commissioning * 5/27-6/30: DRMI commissioning * 7/1-8/9: DRFPMI commissioning * 8/12-10/4: DRFPMI ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Note ==== * Please reduce the number or speed of 16kHz channels. * Summary meeting on tomorrow 11AM. ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * !st Engineering run was successfully finished. * Lock lost was only 3 times after fixing trouble on PR3. * Duty cycle was more than 95%. * PR3 had some glitch or bistable on TM pitch for few urad, probably due to the temperature change around PR area. * DRMI lock was established ~1min. Oscillation introduced fringe jumps and lock was lost. * Y arm lock was tried also. * To check alignment of REFL table. ==== Work plan ==== * Continuously fixing ITMY issue. * CAL: Measurement TF coil driver for ETMs. * IO chassis of EY0 will be exchanged.