=== 2019/6/12(Wed.) === ==== Schedule ==== * --(5/22-23: MZ release from PSL)-- * --(5/20-24: Exchanging cryo valves.)-- * --(5/27-6/2: Y arm mass lock.)-- (not done yet) * --(5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS) )-- * --(6/3-6/8: Installation of TMS for ETMY)-- * --(6/8: Engineering run)-- * ITMX * ETMX * ITMY * ETMY * Long term: * --(4/22-5/31: Yarm commissioning)-- * 5/27-6/30: DRMI commissioning * 7/1-8/9: DRFPMI commissioning * 8/12-10/4: DRFPMI ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Note ==== * Please reduce the number or speed of 16kHz channels. ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * COM: Tried PRMI, but BS yaw fluctuation was large about ~2urad. * Type B: Increasing damping gain for IP yaw of BS did not work so much. ==== Work plan ==== * DGS: Maintenance for exchanging RT-PC today, and fixing Dolphin. * COM: PLL servo will be replaced during maintenance time.