Line 10: Line 10:
 * 6/18 Move PR3

2019/6/18(Tue.)

Schedule

  • 5/22-23: MZ release from PSL

  • 5/20-24: Exchanging cryo valves.

  • 5/27-6/2: Y arm mass lock. (not done yet)

  • 5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS)

  • 6/3-6/8: Installation of TMS for ETMY

  • 6/8: Engineering run

  • 6/18 Move PR3
  • ITMX
  • ETMX
  • ITMY
  • ETMY
  • Long term:
    • 4/22-5/31: Yarm commissioning

    • 5/27-6/30: DRMI commissioning
    • 7/1-8/9: DRFPMI commissioning
    • 8/12-10/4: DRFPMI ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting

Note

  • Please reduce the number or speed of 16kHz channels.

Night work

Weekend

Report of work

  • COM: Tried Yarm mass lock. Due to pitch fluctuation of ETMY, lock was not established.
  • PEM: Wether station started.

Work plan

  • Type Bp: PR3 will be moved today by ~100um, ~2mm
  • CRY: ETMY cryo cooler will be restarted because of meta stable.
  • DMG: Connection of fiber channel to one of the storage in the computer room in mine.