=== 2019/7/8(Mon.) === ==== Schedule ==== * ~7/31: Trial for DRMI with polarization. * 7/6~: Trial for mass lock * ITMX * ETMX * ITMY * 7/4: Turbo pump on * ETMY * 7/4: Turbo pump on * Long term: * --(4/22-5/31: Yarm commissioning)-- * --(5/27-6/30: DRMI commissioning)-- * 7/1-8/9: FPMI/DRFPMI commissioning * 8/12-10/4: ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ==== Note ==== * Please reduce the number or speed of 16kHz channels. * GV of BS side can be opened on 7/5, but still please do not oped are side. ==== Night work ==== ==== Weekend ==== ==== Report of work ==== * X arm: Cause of build up issue was tuned out that calm servo was broken. Transmitted light became stable with another circuit. * OMC: REFL port was consistent with that transmitted light had only 10%. * It means no significant loss inside cavity. * Still cause of 10% is not so sure. It could be mode matching. * CAL: MICH calibration is done. High frequency looks petty flat, ADC noise? Needs check whitening on. * PRM misaligned state did now work. It was tripped. ==== Work plan ==== * SRM needs some tuning, but probably OMC work has higher priority.