Differences between revisions 4 and 5
Revision 4 as of 2018-03-07 12:48:33
Size: 6123
Comment:
Revision 5 as of 2018-03-07 12:59:57
Size: 4827
Comment:
Deletions are marked like this. Additions are marked like this.
Line 32: Line 32:
 * MCT(2018/3/XX Kokeyama)  * PD fot MCT(2018/3/XX Kokeyama)
Line 38: Line 38:
 * PD fot REFL(2018/3/XX Kokeyama)
Line 39: Line 40:
 * GigE camera for
 * Tcam for BS(2018/3/XX 井上)
 * PDで入射ビームのズレを見る準備(2018/3/XX Enomoto)
 * GigE camera for IMMT1(2018/3/XX Kokeyama)
 * GigE camera for IMMT2(2018/3/XX Kokeyama)
 * GigE camera for PRM(2018/3/XX Kokeyama)
 * GigE camera for PR2(2018/3/XX Kokeyama)
 * GigE camera for PR3(2018/3/XX Kokeyama)
 * Tcam for ITMX(2018/3/XX 井上)

 * Vacuum gage(2018/XX/XX 内山)
Line 44: Line 50:
=== その他追加項目 ===
Line 46: Line 51:
 * 真空引き開始前にビーム再チェック(2018/XX/XX Enomoto)
 * 真空引き後、防振系の動作チェック(2018/XX/XX 高橋、牛場) -> 2018/1/23予定
 * ポンプスタート(2018/XX/XX 内山) -> 2018/??/??予定
 * 真空度のチェック(2018/XX/XX 内山) -> 2018/??/??予定
 * ゲードバルブの動作チェック(2018/XX/XX 内山) -> 2018/??/??予定
 * ゲードバルブの開閉モニター (2018/XX/XX 内山) -> 2018/??/??予定
=== Other checks before pump down ===
Line 53: Line 53:
 * Re-checkin beam before pump down(2018/XX/XX Enomoto)
 * Monitor for gate valve open/close (2018/3/XX Uchiyama)
 * Star pump down(2018/XX/XX Uchiyama) -> Planned at 2018/3/19
Line 54: Line 57:
=== Type-A tower (高橋) ===
 * --(BFのチューニング)--(11/28, 高橋)
 * --(F3のチューニング)--(11/30, 高橋・奥富)
 * --(TFのチューニング)--(12/7, 高橋)
 * --(BF damperの位置調整)--(12/7, 高橋)
 * --(IPのセンタリング)--(12/7, 高橋)
 * --(BF FRの動作確認)--(12/8, 高橋・奥富)
 * --(BF yaw picomotorの動作確認)--(高橋・佐藤)
 * --(トップ真空槽蓋閉め)--(12/21, 高橋・佐藤)
 * --(トップ真空槽ボルト閉め)--(12/22, 木村)
 * --(クロス菅ボルト閉め)--(12/22, 木村)->
 * --(IPのDC調整)-- (高橋)
 * --(BFのdamping制御)-- -> (1/13, 牛場)
 * --(BF FRによるmirrorの高さ調整)--(12/21, 高橋)
 * --(BF yaw picomotorによるmirrorのyaw調整)--(12/20, 高橋)
 * --(事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。)--
 * --(BF温度計つなぎこみ)--(2018/1/24 高橋、牛場)
=== Checks during pump down ===

 * Vacuum monitor(2018/XX/XX Uchiyama)
 * 真空引き後、防振系の動作チェック(2018/XX/XX 高橋、牛場)
Line 82: Line 73:
 * --(冷却と主ビーム観測に向けたTcamのセッティング)-- (2017/12/27, 井上, 横澤)
 * --(Gigeカメラの前の真空窓取り外しと取り付け)-- (2017/12/18, 井上)
  * (Gigeカメラのポートにはメタルガスケットが入っていないため、そのまま冷却をスタートしてしまうと真空漏れを起こしミラー表面を汚してしまう。)

Check list for vacuum test in the Center area

  • term: 2018/3/7~ 2018/3/23

Schedule

  • 2018/3/12-17: ducts connection
  • 2018/3/12-16: pump down and leak check


Check items

Each item should have following format;

  • item (checking date, checking person)

Once the item has been checked, it will be like:

  • item (2018/3/10, Somebody)


Alignment

  • Beam check at ETMX (2018/3/5, Enomoto)

  • Beam check at ETMY (2018/3/6, Enomoto)

  • Beam check at REFL (2018/3/6, Enomoto)

  • PD movement from BS are to REFL are (2018/3/XX, Enomoto)

Preparation of monitors during pump down

  • Oplev monitor check for MCI(2018/3/XX Kokeyama)
  • Oplev monitor check for MCE(2018/3/XX Kokeyama)
  • PD fot MCT(2018/3/XX Kokeyama)
  • Oplev monitor check for MCO(2018/3/XX Kokeyama)
  • Oplev monitor check for PRM(2018/3/XX Enomoto)
  • Oplev monitor check for PR2(2018/3/XX Enomoto)
  • Oplev monitor check for PR3(2018/3/XX Enomoto)
  • Oplev monitor check for BS(2018/3/XX Enomoto)
  • PD fot REFL(2018/3/XX Kokeyama)
  • GigE camera for IMMT1(2018/3/XX Kokeyama)
  • GigE camera for IMMT2(2018/3/XX Kokeyama)
  • GigE camera for PRM(2018/3/XX Kokeyama)
  • GigE camera for PR2(2018/3/XX Kokeyama)
  • GigE camera for PR3(2018/3/XX Kokeyama)
  • Tcam for ITMX(2018/3/XX 井上)
  • Vacuum gage(2018/XX/XX 内山)
  • 真空槽の傾きをdial gaugeで測る(2018/3/XX 都丸、鈴木、木村)

Other checks before pump down

  • Re-checkin beam before pump down(2018/XX/XX Enomoto)
  • Monitor for gate valve open/close (2018/3/XX Uchiyama)
  • Star pump down(2018/XX/XX Uchiyama) -> Planned at 2018/3/19

Checks during pump down

  • Vacuum monitor(2018/XX/XX Uchiyama)
  • 真空引き後、防振系の動作チェック(2018/XX/XX 高橋、牛場)

鏡板閉止 (木村)

  • 鏡板取付前の変換フランジ取付 (2017/12/18, 木村)

  • 輻射シールドのシャッター開確認 (2017/12/19, 木村)

  • 当該部のSuper Insulation(SI)取り外し確認 (2018/1/23, 木村)

  • 鏡板取付後のビューポート取付 (2017/12/27, 阿久津)

  • Oplev用の島?取付 (2017/12/27, 阿久津)

EYAチェンバー周り (井上)

  • フォトディテクターの取り外し (2017/12/15, 横澤)

EYV支持構造体のセット確認

  1. コーンベローズ用 3箇所 (2018/X/XX, 木村)
  2. チェンバー本体用 3箇所 <- 真空引き前にフリーにする  (2018/X/XX, 木村)

真空引き開始前後から冷却開始まで (木村)

  1. 真空フランジを開放し、再度閉止した箇所の確認(リーク試験箇所の確定に必要な情報です。)
    • グループ毎の申告による
      • EYV top flange : VIS group (2018/1/24, 高橋)

      • EYAカメラ側鏡板閉止 (2018/1/22, 木村)

      • EYV chamber : CRY group (2017/12/22, 木村+双葉工業)

      • クロス菅鏡板2箇所 : CRY group (2018/1/22, 高橋(ICRR)+双葉工業)

      • ICF253送風機接続ポート: CRY group (2018/1/22, 高橋(ICRR)+双葉工業)

      • φ800サイドフランジ: CRY group (2018/1/23, 都丸+双葉工業)

      • 冷凍機NW-50フランジ交換 4箇所: CRY group (2018/1/23, 木村)

  2. 温度・圧縮機のモニター
    • スタートさせる (2018/XX/XX, 都丸、麻生) -> 2018/1/23予定

    • 温度・圧縮機のループテスト (2018/XX/XX, 都丸、麻生、木村) -> 冷却開始前までに予定

      • 万が一遅れても冷却は遅らせない。ただし、一台すでに壊しているので、注意。
  3. 真空引き
    1. 真空計2台 ON (2018/1/23, 木村)

    2. 粗挽きポンプスタート (2018/1/24, 木村) -> 2018/1/23朝予定

    3. 大まかなリークチェック (2018/1/24, 木村) 1/23に0.1気圧引いてそれが1/24朝まで保たれていたのでOK

    4. ターボポンプ冷却水循環装置スタート (2018/1/23, 木村)

    5. ターボポンプスタート (2018/1/24, 木村) 朝9時30分起動

  4. リーク試験 (2017/XX/XX, 木村、上田、高橋(icrr)) -> 2018/1/29,30予定

    • (リーク判定 < 1x10-10 Pa・m3/s)

    • EYA arm側ゲートバルブ動作チェック (2018/XX/XX, 木村) -> 2018/1/30夕予定?

    • EYA arm側ゲートバルブOPEN (2018/XX/XX, 木村) -> 2018/1/30夕予定?

    • メインレーザーを使ったバッフルPDの動作確認 (2018/XX/XX, 和泉?) -> 2018/1/30夕予定?

KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter (last edited 2018-03-14 17:10:07 by OsamuMiyakawa)