Differences between revisions 41 and 42
Revision 41 as of 2018-03-14 13:08:23
Size: 7372
Comment:
Revision 42 as of 2018-03-14 15:32:01
Size: 6774
Comment:
Deletions are marked like this. Additions are marked like this.
Line 76: Line 76:
 * hemisphere(VM7950)φ 1000/400 L 570 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX  * --(hemisphere(VM7950)φ 1000/400 L 570)-- (2018/3/14 Kimura)
Line 79: Line 79:
 * pump port (VL7862C) φ 800 L 1285 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX  * --(pump port (VL7862C) φ 800 L 1285)-- (2018/3/14 Kimura)
Line 82: Line 82:
 * bellows (VL7952A) φ 400 L 555 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX  * --(bellows (VL7952A) φ 400 L 555)-- (2018/3/14 Kimura)
Line 85: Line 85:
 * bellows (VL7856) φ 800 L 620 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * pump port (VL8423) φ 800 L 760 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * bellows (VL7856) φ 800 L 620 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * --(bellows (VL7856) φ 800 L 620)-- (2018/3/14 Kimura)
 * --(pump port (VL8423) φ 800 L 760)-- (2018/3/14 Kimura)
 * --(bellows (VL7856) φ 800 L 620)-- (2018/3/14 Kimura)
Line 90: Line 90:
 * bellows (VL7856) φ 800 L 620 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * pump port (VL8428) φ 800 L 8225 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * bellows (VL7856) φ 800 L 620 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * --(bellows (VL7856) φ 800 L 620)-- (2018/3/14 Kimura)
 * --(pump port (VL8428) φ 800 L 8225)-- (2018/3/14 Kimura)
 * --(bellows (VL7856) φ 800 L 620)-- (2018/3/14 Kimura)
Line 95: Line 95:
 * bellows (VL7856) φ 800 L 620 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * pump port (VL8425) φ 800 L 1740 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * bellows (VL7856) φ 800 L 620 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * --(bellows (VL7856) φ 800 L 620)-- (2018/3/14 Kimura)
 * --(pump port (VL8425) φ 800 L 1740)-- (2018/3/14 Kimura)
 * --(bellows (VL7856) φ 800 L 620)-- (2018/3/14 Kimura)
Line 100: Line 100:
 * bellows (VL7855) φ 1000 L 620 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * pump port (VL8419) φ 1000 L 4376 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * bellows (VL7857D) φ 1000 L 620 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * --(bellows (VL7855) φ 1000 L 620)-- (2018/3/14 Kimura)
 * --(pump port (VL8419) φ 1000 L 4376)-- (2018/3/14 Kimura)
 * --(bellows (VL7857D) φ 1000 L 620)-- (2018/3/14 Kimura)
Line 106: Line 106:
 * bellows/tube (VL7860) φ 1000 L 1765 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * pump port (VL7861) φ 1000 L 1400 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX
 * --(bellows/tube (VL7860) φ 1000 L 1765)-- (2018/3/14 Kimura)
 * --(pump port (VL7861) φ 1000 L 1400)-- (2018/3/14 Kimura)
Line 111: Line 111:
 * blank φ 800 (2018/3/XX Uchiyama) -> Planned at 2018/3/XX  * --(blank φ 800)-- (2018/3/14 Kimura)
Line 117: Line 117:
  * IFF の、プラスY側のφ400のフランジ。Oringはついてないのでつける必要がある。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
  * IMMの、マイナスY側のφ400のフランジ。Oringはついてないのでつける必要がある。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
  * --(IFF の、プラスY側のφ400のフランジ。Oringはついてないのでつける必要がある。)-- (2018/3/14 Kimura)
  * --(IMMの、マイナスY側のφ400のフランジ。Oringはついてないのでつける必要がある。)-- (2018/3/14 Kimura)
Line 122: Line 122:
   * トップフランジ: O-ringを入れてあるが,養生テープが貼ったまま。締められていない。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
   * 上部サービスフランジ2枚(添付写真): 蓋は付いているが,締めていない。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
   * 下部サービスフランジ2枚(添付写真): 蓋は付いているが,締めていない。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
   * フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
   * フィードスルーフランジを取り付けるポートに付いているメクラフランジ: ちゃんと締めていない。ガスケットも入っていないかもしれない。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
   * --(トップフランジ: O-ringを入れてあるが,養生テープが貼ったまま。締められていない。)-- (2018/3/14 Kimura)
   * --(上部サービスフランジ2枚(添付写真): 蓋は付いているが,締めていない。)-- (2018/3/14 Kimura)
   * --(下部サービスフランジ2枚(添付写真): 蓋は付いているが,締めていない。)-- (2018/3/14 Kimura)
   * --(フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。)-- (2018/3/14 Kimura)
   * --(フィードスルーフランジを取り付けるポートに付いているメクラフランジ: ちゃんと締めていない。ガスケットも入っていないかもしれない。)-- (2018/3/14 Kimura)
Line 130: Line 130:
   * 各側面フランジをクロークランプにより締め付ける。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
   * --(各側面フランジをクロークランプにより締め付ける。)-- (2018/3/14 Kimura)
Line 134: Line 133:
   * フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
   * グリーン入射用ビューポートのフランジ: ガスケットは入れてあるが,ちゃんと締めていない。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
   * --(フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。)-- (2018/3/14 Kimura)
   * --(グリーン入射用ビューポートのフランジ: ガスケットは入れてあるが,ちゃんと締めていない。)-- (2018/3/14 Kimura)
Line 137: Line 136:
   * 各側面フランジをクロークランプにより締め付ける。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
   * --(各側面フランジをクロークランプにより締め付ける。)-- (2018/3/14 Kimura)
Line 141: Line 139:
   * フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
   * 各側面フランジをクロークランプにより締め付ける。 (2018/3/XX Kimura) -> Planned at 2018/3/XX
   * --(フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。)-- (2018/3/14 Kimura)
   * --(各側面フランジをクロークランプにより締め付ける。)-- (2018/3/14 Kimura)

Check list for vacuum test in the Center area

  • Term: 2018/3/7~2018/3/23

Schedule

  • 2018/3/12-14: ducts connection
  • 2018/3/15-16: pump down
  • 2018/3/19-23: leak check


Check items

Each item should have following format;

  • item (checking date, checking person) -> Planned at 2018/3/XX

Once the item has been checked, it will be like:

  • item (2018/3/10, Somebody)


Alignment

  • Beam check at ETMX (2018/3/5, Enomoto)

  • Beam check at ETMY (2018/3/6, Enomoto)

  • Beam check at REFL (2018/3/6, Enomoto)

  • PD movement from BS are to REFL area (2018/3/7, Enomoto)

Preparation of monitors during pump down

  • Oplev monitor check for PRM (2018/3/XX Kokeyama) -> 2018/3/14 planed by Kokeyama

  • Oplev monitor check for PR2 (2018/3/14 Enomoto)

  • Oplev monitor check for PR3 (2018/3/14 Enomoto)

  • Oplev monitor check for BS (2018/3/14 Enomoto) -> 2018/3/14 planed

  • PD for REFL (2018/3/14 Enomoto)

  • GigE camera for IMMT1 (2018/3/7 Kokeyama)

  • GigE camera for IMMT2 (2018/3/7 Kokeyama)

  • GigE camera for PR2 (2018/3/7 Kokeyama)

  • GigE camera for PR3 (2018/3/7 Kokeyama)

  • GigE camera for BS (2018/3/7 Kokeyama)

  • GigE camera for REFL (2018/3/ Kokeyama)

  • Tcam for IXC (2018/3/14 Yokozawa)

  • Tcam for IYC (2018/3/14 Yokozawa)

  • Vacuum gage (2018/XX/XX Uchiyama) -> Planned at 2018/3/XX

  • 真空槽の傾きをdial gaugeで測る準備 (2018/3/14 Kimura)


Other checks before pump down

  • Re-checkin beam before pump down (2018/3/XX Enomoto) -> Planned at 2018/3/14 night

  • Control and Monitor for gate valve open/close (2018/3/XX Uchiyama) -> Planned at 2018/3/XX

  • Star pump down(2018/3/XX Uchiyama) -> Planned at 2018/3/15

Pump down (Kimura)

  1. 真空計 ON (2018/3/XX, Kimura) -> Planned at 2018/3/15

  2. 粗挽きポンプスタート (2018/3/XX, Kimura) -> Planned at 2018/3/15

  3. ターボポンプ冷却水循環装置スタート (2018/3/XX, Kimura) -> Planned at 2018/3/16

  4. ターボポンプスタート (2018/3/XX, Kimura) -> Planned at 2018/3/16

  5. リーク試験 (2018/3/XX, Kimura) -> Planned at 2018/3/19-21

    • (リーク判定 < 1x10-10 Pa・m3/s)

Checks during pump down

  • Vacuum monitor (2018/XX/XX Uchiyama) -> Planned at 2018/3/XX

  • Oplevで随時アラインメントのチェック (2018/XX/XX Enomono) -> Planned at 2018/3/XX

  • 真空槽の傾きをdial gaugeを見続ける (2018/3/XX, Kimura) -> Planned at 2018/3/XX


Connection status (Uchiyama)

KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter/図2_180208_中央真空系.png

GVmc

  • hemisphere(VM7950)φ 1000/400 L 570 (2018/3/14 Kimura)

IFI

  • pump port (VL7862C) φ 800 L 1285 (2018/3/14 Kimura)

IMM

  • bellows (VL7952A) φ 400 L 555 (2018/3/14 Kimura)

PRM

  • bellows (VL7856) φ 800 L 620 (2018/3/14 Kimura)

  • pump port (VL8423) φ 800 L 760 (2018/3/14 Kimura)

  • bellows (VL7856) φ 800 L 620 (2018/3/14 Kimura)

PR3

  • bellows (VL7856) φ 800 L 620 (2018/3/14 Kimura)

  • pump port (VL8428) φ 800 L 8225 (2018/3/14 Kimura)

  • bellows (VL7856) φ 800 L 620 (2018/3/14 Kimura)

PR2

  • bellows (VL7856) φ 800 L 620 (2018/3/14 Kimura)

  • pump port (VL8425) φ 800 L 1740 (2018/3/14 Kimura)

  • bellows (VL7856) φ 800 L 620 (2018/3/14 Kimura)

BS

  • bellows (VL7855) φ 1000 L 620 (2018/3/14 Kimura)

  • pump port (VL8419) φ 1000 L 4376 (2018/3/14 Kimura)

  • bellows (VL7857D) φ 1000 L 620 (2018/3/14 Kimura)

GVbsx

BS

  • bellows/tube (VL7860) φ 1000 L 1765 (2018/3/14 Kimura)

  • pump port (VL7861) φ 1000 L 1400 (2018/3/14 Kimura)

GVbsy

BS

  • blank φ 800 (2018/3/14 Kimura)


以下、VIS,IOOに他に閉めるべきフランジがないかどうか確認してもらって作ったリスト

  • IFI, IMMの真空容器の状況
    • IFF の、プラスY側のφ400のフランジ。Oringはついてないのでつける必要がある。 (2018/3/14 Kimura)

    • IMMの、マイナスY側のφ400のフランジ。Oringはついてないのでつける必要がある。 (2018/3/14 Kimura)

  • VIS関連チャンバーの状況
    • BS:
      • トップフランジ: O-ringを入れてあるが,養生テープが貼ったまま。締められていない。 (2018/3/14 Kimura)

      • 上部サービスフランジ2枚(添付写真): 蓋は付いているが,締めていない。 (2018/3/14 Kimura)

      • 下部サービスフランジ2枚(添付写真): 蓋は付いているが,締めていない。 (2018/3/14 Kimura)

      • フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。 (2018/3/14 Kimura)

      • フィードスルーフランジを取り付けるポートに付いているメクラフランジ: ちゃんと締めていない。ガスケットも入っていないかもしれない。 (2018/3/14 Kimura)

    • PRM:
      • トップフランジ: O-ringが入っていない。 (2018/3/7 Kimura)

      • フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。 (2018/3/7 Kimura)

      • 各側面フランジをクロークランプにより締め付ける。 (2018/3/14 Kimura)

    • PR2:
      • トップフランジ: O-ringは入っているが締めていない。 (2018/3/5締めた Uchiyama) -> Planned at 2018/3/XX

      • フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。 (2018/3/14 Kimura)

      • グリーン入射用ビューポートのフランジ: ガスケットは入れてあるが,ちゃんと締めていない。 (2018/3/14 Kimura)

      • PR2側面フランジのユーティリティ用フランジ(ICF203、空気導入口として使用)の交換 1箇所の締め付け (2018/3/7 Kimura)

      • 各側面フランジをクロークランプにより締め付ける。 (2018/3/14 Kimura)

    • PR3:
      • トップフランジ: O-ringは入っているが締めていない。(2018/3/5締めた Uchiyama) -> Planned at 2018/3/XX

      • フィードスルーフランジ: ガスケットは入れてあるが,ちゃんと締めていない。 (2018/3/14 Kimura)

      • 各側面フランジをクロークランプにより締め付ける。 (2018/3/14 Kimura)

KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter (last edited 2018-03-14 17:10:07 by OsamuMiyakawa)