== Check list for ETMX vacuum 20180314 == == Check list for ETMX vacuum in spring, 2018 ==

 * Term: ~2018/4/20

=== Schedule ===

 * 2018/3/26-4/6 : ETMX control test
 * 2018/4/9-12 : Closing EXC
 * 2018/4/5(Thur) 12:30 at fan hut.
 * 2018/4/11(Wed) 12:30 at fan hut.
 * 2018/4/12- : pump down
 * 2018/4/18-20: leak check

------
Line 12: Line 25:
 * Beam check at ETMX (2018/X/XX, Enomoto)
 * Beam check at ETMY (2018/X/XX, Enomoto)
 * Beam check at REFL (2018/X/XX, Enomoto)
 * Beam check at ETMX just before pump down(not possible with baffle PD through gate valve?) (2018/X/XX, Enomoto) -> Planned at 2018/4/11
 * Beam check at ETMY just before pump down (2018/X/XX, Enomoto) -> Planned at 2018/4/11
 * Beam check at REFL just before pump down (2018/X/XX, Enomoto) -> Planned at 2018/4/11
Line 19: Line 32:
 * Oplev monitor check for PRM (2018/X/XX Enomoto) -> Planned at 2018/X/XX
 * Oplev monitor check for PR2 (2018/X/XX Enomoto) -> Planned at 2018/X/XX
 * Oplev monitor check for PR3 (2018/X/XX Enomoto) -> Planned at 2018/X/XX
 * Oplev monitor check for BS (2018/X/XX Enomoto) -> Planned at 2018/X/XX
 * PD fot REFL (2018/3/XX Kokeyama) -> Planned at 2018/X/XX

 * GigE camera for IMMT1 (2018/X/XX Kokeyama) -> Planned at 2018/X/XX
 * GigE camera for IMMT2 (2018/X/XX Kokeyama) -> Planned at 2018/X/XX
 * GigE camera for PR2 (2018/X/XX Kokeyama) -> Planned at 2018/X/XX
 * GigE camera for PR3 (2018/X/XX Kokeyama) -> Planned at 2018/X/XX
 *
Tcam for ETMX (2018/X/XX Inoue) -> Planned at 2018/3/XX

 * Vacuum gage (2018/XX/XX Uchiyama) -> Planned at 2018/X/XX
 * 真空槽の傾きをdial gaugeで測る。 (2018/3/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/3/XX
 * Oplev monitor check for PRM (2018/X/XX Enomoto) -> Planned at 2018/4/11
 * Oplev monitor check for PR2 (2018/X/XX Enomoto) -> Planned at 2018/4/11
 * Oplev monitor check for PR3 (2018/X/XX Enomoto) -> Planned at 2018/4/11
 * Oplev monitor check for BS (2018/X/XX Enomoto) -> Planned at 2018/4/11
 * PD fot REFL (2018/4/XX Enomoto) -> Planned at 2018/4/11

 * GigE camera for IMMT1 (2018/X/XX Kokeyama) -> Planned at 2018/4/11
 * GigE camera for IMMT2 (2018/X/XX Kokeyama) -> Planned at 2018/4/11
 * GigE camera for PR2 (2018/X/XX Kokeyama) -> Planned at 2018/4/11
 * GigE camera for PR3 (2018/X/XX Kokeyama) -> Planned at 2018/4/11
 * GigE camera for BS (2018/X/XX Kokeyama) -> Planned at 2018/4/11
 * GigE camera for REFL (2018/X/XX Kokeyama) -> Planned at 2018/4/11

 * --(
Tcam for ETMX)-- (2018/4/11 Inoue)
 * --(Tcam for ETMY)-- (2018/4/11 Inoue)
 * --(Tcam for ITMX)-- (2018/4/5 Inoue)
 * --(Tcam for ITMY)-- (2018/4/5 Inoue)
 * --(Illuminator for ETMX)-- (2018/4/5 Yokozawa)
 * --(Illuminator for ETMY)-- (2018/4/5 Inoue)


 * Vacuum gage for X end (2018/4/XX Inoue) -> Planned at 2018/4/16
 * Vacuum gage for X arm (2018/4/XX Inoue) -> Planned at 2018/4/16
 * Vacuum gage for Y arm (2018/4/XX Inoue) -> Planned at 2018/4/16
 * Vacuum gage for IXA arm (2018/4/XX Inoue) -> Planned at 2018/4/16
 * Vacuum gage for IYA arm (2018/4/XX Inoue) -> Planned at 2018/4/16
 * Vacuum gage for PRM-PR2 (2018/4/XX Inoue) -> Planned at 2018/4/16

 * 真空槽の傾きをdial gaugeで測る。 (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/13
 * Xend 機器制御 for status monitors (2018/4
/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/5, 6
 * Vacuum gauge monitor at the control room at least one location (2018/X/XX Uchiyama, Kimura, Inoue, Miyoki) -> Planned at 2018/4/XX
Line 37: Line 66:
 * --(EQ stopの隙間のチェック5mm程度)--(2018/1/17 都丸、牛場)
 * 1/26に真空引き後、防振系の動作チェック(2018/XX/XX 高橋、牛場) -> 2018/1/23予定
 * 冷却開始前にビーム再チェック(2018/XX/XX 和泉) -> 2018/1/26予定
 * アームのポンプスタート(2018/XX/XX 内山) -> 2018/??/??予定
 * アームの真空度のチェック(2018/XX/XX 内山) -> 2018/??/??予定
 * ゲードバルブの動作チェック(2018/XX/XX 内山) -> 2018/??/??予定
 * ゲードバルブの開閉モニター (2018/XX/XX 内山) -> 2018/??/??予定
 * EQ stopの隙間のチェック5mm程度 (2018/X/XX, Ushiba, Tomaru) -> (2018/4/11 planed)
 * 真空引き後、防振系の動作チェック (2018/X/XX, Enomoto) -> (2018/4/13 planed)
 * EXA ゲードバルブの動作チェック (2018/X/XX, Uchiyama) -> (2018/4/20 planed)
 * EXA ゲードバルブの開閉モニター to 機器制御 (今回は必須でないかもしれない) (2018/X/XX, Uchiyama) -> (2018/4/20 planed)
 * ダストウィットネスサンプル設置 (2018/X/XX, Hirose, Nakano) -> (2018/4/12 morning planed)
Line 47: Line 73:
 * Tuning of BF (2018/X/XX, Takahashi) -> (2018/X/XX planed)
 * Tuning of F3 (2018/X/XX, Takahashi) -> (2018/X/XX planed)
 * Tuning of TF (2018/X/XX, Takahashi) -> (2018/X/XX planed)
 * Tuning of position of BF damper (2018/X/XX, Takahashi) -> (2018/X/XX planed)
 * Centering IP (2018/X/XX, Takahashi) -> (2018/X/XX planed)
 * Fishing rodの動作チェック (2018/X/XX, Takahashi) -> (2018/4/6 planed, without camera)
 * --(Tuning of BF)-- (2018/3/26, Takahashi)
 * --(Tuning of F3)-- (2018/3/27, Takahashi)
 * --(Tuning of TF)-- (2018/3/27, Takahashi)
 * --(Tuning of position of BF damper)-- (2018/3/28, Takahashi)
 * --(Centering IP)-- (2018/3/27, Takahashi)
Line 54: Line 81:
 * トップ真空槽蓋閉め (2018/X/XX, Takahashi) -> (2018/X/XX planed)
 * トップ真空槽ボルト閉め (2018/X/XX, Kimura) -> (2018/X/XX planed)
 * クロス菅ボルト閉め (2018/X/XX, Kimura) -> (2018/X/XX planed)
 * IPのDC調整 (2018/X/XX, Takahashi) -> (2018/X/XX planed)
 *
BFのdamping制御 (2018/X/XX, Ushiba) -> (2018/X/XX planed)
 * BF FRによるmirrorの高さ調整 (2018/X/XX, Takahashi) -> (2018/X/XX planed)
 *
BF yaw picomotorによるmirrorのyaw調整 (2018/X/XX, Takahashi) -> (2018/X/XX planed)
 *
事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。 (2018/X/XX, ??) -> (2018/X/XX planed)
 * BF温度計つなぎこみ (2018/X/XX, Takahashi, Ushiba) -> (2018/X/XX planed)
 * --(トップ真空槽蓋閉め)-- (2018/3/28, Takahashi)
 * トップ真空槽ボルト閉め (2018/X/XX, Kimura) -> (2018/4/10 planed)
 * クロス菅ボルト閉め (2018/X/XX, Kimura) -> (2018/4/10 planed)
 * IPの制御 (2018/4/XX, Okutomi) -> (2018/X/XX re-check)
 * --(
BFのdamping制御)-- (2018/4/2, Okutomi) -> (2018/X/XX planed)
 * --(BF FRによるmirrorの高さ調整)-- (2018/4/5, Takahashi)
 * --(
BF yaw picomotorによるmirrorのyaw調整)-- (2018/4/5, Ushiba)
 * --(
事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。)-- (2018/4/5, Ushiba)
 * BF温度計つなぎこみ (2018/X/XX, Takahashi, Ushiba) -> (2018/4/6 planed)
Line 65: Line 93:

 * --(鏡板取付前の変換フランジ取付)-- (2017/12/18, 木村)
 * --(輻射シールドのシャッター開確認)-- (2017/12/19, 木村)
 * --(当該部のSuper Insulation(SI)取り外し確認)-- (2018/1/23, 木村)
 * --(鏡板取付後のビューポート取付)-- ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=3909|2017/12/27]], 阿久津)
 * --(Oplev用の島?取付)-- ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=3910|2017/12/27]], 阿久津)

=== EYAチェンバー周り (井上) ===
 * --(フォトディテクターの取り外し)-- (2017/12/15, 横澤)
 * --(冷却と主ビーム観測に向けたTcamのセッティング)-- (2017/12/27, 井上, 横澤)
 * --(Gigeカメラの前の真空窓取り外しと取り付け)-- (2017/12/18, 井上)
  * (Gigeカメラのポートにはメタルガスケットが入っていないため、そのまま冷却をスタートしてしまうと真空漏れを起こしミラー表面を汚してしまう。)

=== EYV支持構造体のセット確認 ===
 1. コーンベローズ用 3箇所 (2018/X/XX, 木村)
 * チェンバー本体用 3箇所 <- 真空引き前にフリーにする  (2018/X/XX, 木村)

=== 真空引き開始前後から冷却開始まで (木村) ===
 * 8K および 80Kシールドにつける窓類の取り付け (2018/4/xx, Ushiba) -> (2018/4/11 just before closing EXC door)
 * --(輻射シールドのシャッター開確認)-- (2018/4/5, Ushiba)
 * 当該部のSuper Insulation(SI)取り外し確認 (2018/X/XX, Kimura) -> (2018/X/XX planed)
 * 鏡板取付前の変換フランジ取付 (2018/X/XX, Kimura) -> (2018/4/9 planed)
 * 鏡板取付後のビューポート取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed)
 * Oplev用の島取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed)

=== EXAチェンバー周り (Inoue) ===
 * --(フォトディテクターの取り外し)-- (2018/3/26, Yokozawa)
 * GigEカメラの前の真空窓取り外しと取り付け (2018/X/XX, Inoue) -> (2018/4/9 planed)

=== EXV支持構造体のセット確認 ===
 1. コーンベローズ用が固定されているかの確認 3箇所 (2018/4/9, 木村)
 * --(チェンバー本体用 3箇所 <- 真空引き前にフリーにする)-- 今回はやらない

=== 真空引き開始前後 (木村) ===
Line 86: Line 112:
   * --(EYV top flange)-- : VIS group (2018/1/24, 高橋)
   * --(EYAカメラ側鏡板閉止)-- (2018/1/22, 木村)
   * --(EYV chamber)-- : CRY group (2017/12/22, 木村+双葉工業)
   * --(クロス菅鏡板2箇所)-- : CRY group (2018/1/22, 高橋(ICRR)+双葉工業)
   * --(ICF253送風機接続ポート)--: CRY group (2018/1/22, 高橋(ICRR)+双葉工業)
   * --(φ800サイドフランジ)--: CRY group (2018/1/23, 都丸+双葉工業)
   * --(冷凍機NW-50フランジ交換)-- 4箇所: CRY group (2018/1/23, 木村)

 * 温度・圧縮機のモニター
  * スタートさせる (2018/XX/XX, 都丸、麻生) -> 2018/1/23予定

   * EXA 鏡板閉止 (2018/4/XX, Kimura) -> (2018/4/10-12 planed)
   * EXV top flange: VIS group (2018/X/XX, Kimura) -> (2018/4/10-12 planed)
   * --(EXV ICF flange交換 ICF203/NW50 変換フランジ -> ICF203ブランクフランジ)-- : VIS group (2018/3/28, Takahashi)
   * クロス菅鏡板2箇所: CRY group, VIS group (2018/X/XX, Kimura) -> (2018/4/10-12 planed)
   * ICF253送風機接続ポート: CRY group (2018/X/XX, , Kimura) -> (2018/4/10-12 planed)
   * EXC鏡板2箇所: CRY group (2018/X/XX, Kimura) -> (2018/4/11,12 planed)
   * EXC View''''''Port 3箇所(鏡板1箇所、--(容器2箇所)--):AOS (2018/X/XX, Akutsu) -> (2018/4/12 planed)
   * 冷凍機NW-50フランジ交換 4箇所: CRY group (2018/X/XX, Kimura) -> (2018/4/10-12 planed)
   * EXA ICF152 2箇所: cal group (2018/4/5-6, Inoue) -> (2018/4/9 planed)

 * 真空引き
  i. 真空計2台 ON (2018/X/XX, Kimura) -> (2018/4/13 planed)
  * 粗挽きポンプスタート (2018/X/XX, Kimura) -> (2018/4/13 planed)
  * 大まかなリークチェック (2018/X/XX, Kimura) -> (2018/4/13 planed)
  * ターボポンプ冷却水循環装置スタート (2018/X/XX, Kimura) -> (2018/4/16 planed)
  * ターボポンプスタート (2018/X/XX, Kimura) -> (2018/4/16 planed)


 * リーク試験 (2018/4/XX, Kimura) -> (2018/4/18-20 planed)
   * (リーク判定 < 1x10^-10 Pa・m^3/s)

 * ゲートバルブ動作試験 (2018/4/XX, Kimura) -> (2018/4/20 planed)


 * (温度・圧縮機のモニター)
  * スタートさせる (2018/XX/XX, 都丸、麻生) -> (2018/X/XX planed)
Line 97: Line 140:
   * 万が一遅れても冷却は遅らせない。ただし、一台すでに壊しているので、注意。

 * 真空引き
  i. --(真空計2台 ON)-- (2018/1/23, 木村)
  * --(粗挽きポンプスタート)-- (2018/1/24, 木村) -> 2018/1/23朝予定
  * --(大まかなリークチェック)-- (2018/1/24, 木村) 1/23に0.1気圧引いてそれが1/24朝まで保たれていたのでOK
  * --(ターボポンプ冷却水循環装置スタート)-- (2018/1/23, 木村)
  * --(ターボポンプスタート)-- (2018/1/24, 木村) 朝9時30分起動

 * リーク試験 (2017/XX/XX, 木村、上田、高橋(icrr)) -> 2018/1/29,30予定
  * (リーク判定 < 1x10^-10 Pa・m^3/s)
  * EYA arm側ゲートバルブ動作チェック (2018/XX/XX, 木村) -> 2018/1/30夕予定?
  * EYA arm側ゲートバルブOPEN (2018/XX/XX, 木村) -> 2018/1/30夕予定?
  * メインレーザーを使ったバッフルPDの動作確認 (2018/XX/XX, 和泉?) -> 2018/1/30夕予定?

 * 冷却開始
  i. ヘリウム圧縮機用冷却水循環装置 1次冷却水バルブ 開 (2017/XX/XX, 木村) -> 2018/1/25夕方予定
  * ヘリウム圧縮機用冷却水循環装置 ON (2017/XX/XX, 木村) -> 2018/1/25夕方予定
  * ヘリウム圧縮機 6台 ON (2017/XX/XX, 木村) -> 2018/1/25夕方予定
Line 122: Line 145:
  * --(PFのリリース(16箇所))--(2017/12/20, 牛場、都丸)
  * --(MNのリリース(16箇所))--(2017/12/20, 牛場、都丸)
  * --(MNRのリリース(16箇所))--(2017/12/20, 牛場、都丸)
  * --(IMのリリース(6箇所))--(2017/12/20, 牛場、都丸)
  * --(IMRのリリース(16箇所))--(2017/12/20, 牛場、都丸)
  * --(TMのリリース(16箇所))--(2017/12/20, 牛場、都丸)
  * --(TMRのリリース(15箇所))--(2017/12/20, 牛場、都丸)
  * PFのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
  * MNのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
  * MNRのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
  * IMのリリース(6箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
  * IMRのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
  * TMのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
  * TMRのリリース(15箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)
Line 131: Line 154:
  * --(TM Op''''''Lev Pitch:キャリブレーション済み)--(2017/12/08,牛場、宮本)
  * --(TM Op''''''Lev Yaw:キャリブレーション済み)--(2017/12/08,牛場、宮本)
  * TM Op''''''Lev Length:未確認 -> 真空引き以降に予定


  * --(IM PS H1:動作確認済み)--(2017/12/21,牛場、宮本)
  * --(IM PS H2:動作確認済み)--(2017/12/21,牛場、宮本)
  * --(IM PS H3:動作確認済み)--(2017/12/21,牛場、宮本)
  * --(IM PS V1:動作確認済み)--(2017/12/21,牛場、宮本)
  * --(IM PS V2:動作確認済み)--(2017/12/21,牛場、宮本)
  * --(IM PS V3:動作確認済み)--(2017/12/21,牛場、宮本)

  * --(MN PS H1:動作確認済み)--(2017/12/21,牛場、宮本)
  * --(MN PS H2:動作確認済み)--(2017/12/21,牛場、宮本)
  * --(MN PS H3:動作確認済み)--(2017/12/21,牛場、宮本)
  * --(MN PS V1:動作確認済み)--(2017/12/21,牛場、宮本)
  * --(MN PS V2:動作確認済み)--(2017/12/21,牛場、宮本)
  * --(MN PS V3:動作確認済み)--(2017/12/21,牛場、宮本)

  * --(MN Op''''''Lev Pitch: 実装したが要確認)-- -> (2018/1/23, 牛場) -> 2018/1/17予定
  * --(MN Op''''''Lev Yaw: 実装したが要確認)-- -> (2018/1/23, 牛場) -> 2018/1/17予定

  * --(温度計A:接続確認済み)--(2017/12/21,牛場)
  * --(温度計C:接続確認済み)--(2017/12/21,牛場)
  * --(温度計D:接続確認済み)--(2017/12/21,牛場)
  * --(温度計E:接続確認済み)--(2017/12/21,牛場)
  * --(温度計F:接続確認済み)--(2017/12/21,牛場)
  * 温度計G:出力不良、真空槽外配線が原因 (2018/1/XX,牛場、宮本) -> 原因はある程度特定できたがまだ未解決
  * --(温度計H:接続確認済み)--(2017/12/21,牛場)
  * --(TM Op''''''Lev Pitch)-- (2018/3/30, Ushiba, Tomaru)
  * --(TM Op''''''Lev Yaw)-- (2018/3/30, Ushiba, Tomaru)
  * TM Op''''''Lev Length (2018/X/XX, Ushiba, Tomaru) -> (2018/4/16 planed)


  * --(IM PS H1)-- (2018/4/5, Ushiba)
  * --(IM PS H2)-- (2018/4/5, Ushiba)
  * --(IM PS H3)-- (2018/4/5, Ushiba)
  * --(IM PS V1)-- (2018/4/5, Ushiba)
  * --(IM PS V2)-- (2018/4/5, Ushiba)
  * --(IM PS V3)-- (2018/4/5, Ushiba)

  * --(MN PS H1)-- (2018/4/5, Ushiba)
  * --(MN PS H2)-- (2018/4/6, Ushiba)
  * --(MN PS H3)-- (2018/4/5, Ushiba)
  * --(MN PS V1)-- (2018/4/5, Ushiba)
  * --(MN PS V2)-- (2018/4/5, Ushiba)
  * --(MN PS V3)-- (2018/4/5, Ushiba)

  * MN Op''''''Lev Pitch (2018/X/XX, Miyamoto) -> (2018/4/12 planed)
  * MN Op''''''Lev Yaw (2018/X/XX, Miyamoto) -> (2018/4/12 planed)

  * 温度計A (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計B (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計C (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計D (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計E (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計F (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計G (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
  * 温度計H (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
Line 163: Line 187:
  * --(TM アクチュエータ H1:動作確認済み)--(2017/12/11,牛場、宮本、長谷川、田中)
  * --(TM アクチュエータ H2:動作確認済み)--(2017/12/11,牛場、宮本、長谷川、田中)
  * --(TM アクチュエータ H3:動作確認済み)--(2017/12/11,牛場、宮本、長谷川、田中)
  * --(TM アクチュエータ H4:動作確認済み)--(2017/12/11,牛場、宮本、長谷川、田中)

  * --(IM アクチュエータ H1:動作確認済み)--(2017/12/15,牛場、宮本、長谷川)
  * --(IM アクチュエータ H2:動作確認済み)--(2017/12/15,牛場、宮本、長谷川)
  * --(IM アクチュエータ H3:動作確認済み)--(2017/12/15,牛場、宮本、長谷川)
  * --(IM アクチュエータ V1:動作確認済み)--(2017/12/15,牛場、宮本、長谷川)
  * --(IM アクチュエータ V2:動作確認済み)--(2017/12/15,牛場、宮本、長谷川)
  * --(IM アクチュエータ V3:動作確認済み)--(2017/12/15,牛場、宮本、長谷川)

  * --(MN アクチュエータ H1:動作確認済み)--(2017/12/15,牛場、宮本、長谷川)
  * --(MN アクチュエータ H2:動作確認済み)--(2017/12/15,牛場、宮本、長谷川)
  * --(MN アクチュエータ H3:動作確認済み)--(2017/12/15,牛場、宮本、長谷川)
  * --(MN アクチュエータ V1:動作確認済み)--(2017/12/15,牛場、宮本、長谷川)
  * --(MN アクチュエータ V2:動作確認済み)--(2017/12/15,牛場、宮本、長谷川)
  * --(MN アクチュエータ V3:動作確認済み)--(2017/12/15,牛場、宮本、長谷川)

  * --(SBS ダンピングコイル(V1-V4):接続確認済み)--(2017/12/??,牛場)

  * --(MN moving mass1:動作確認済み)--(2017/12/15,牛場、都丸)
  * --(MN moving mass2:動作確認済み)--(2017/12/15,牛場、都丸)
  * --(PF moving mass1:動作確認済み)--(2017/12/15,牛場、都丸)
  * --(PF moving mass2:動作確認済み)--(2017/12/15,牛場、都丸)
  * --(TM アクチュエータ H1)-- (2018/4/5, Ushiba)
  * --(TM アクチュエータ H2)-- (2018/4/5, Ushiba)
  * --(TM アクチュエータ H3)-- (2018/4/5, Ushiba)
  * --(TM アクチュエータ H4)-- (2018/4/5, Ushiba)

  * --(IM アクチュエータ H1)-- (2018/4/5, Ushiba)
  * --(IM アクチュエータ H2)-- (2018/4/5, Ushiba)
  * --(IM アクチュエータ H3)-- (2018/4/5, Ushiba)
  * --(IM アクチュエータ V1)-- (2018/4/5, Ushiba)
  * --(IM アクチュエータ V2)-- (2018/4/5, Ushiba)
  * --(IM アクチュエータ V3)-- (2018/4/5, Ushiba)

  * --(MN アクチュエータ H1)-- (2018/4/5, Ushiba)
  * --(MN アクチュエータ H2)-- (2018/4/5, Ushiba)
  * --(MN アクチュエータ H3)-- (2018/4/5, Ushiba)
  * --(MN アクチュエータ V1)-- (2018/4/5, Ushiba)
  * --(MN アクチュエータ V2)-- (2018/4/5, Ushiba)
  * --(MN アクチュエータ V3)-- (2018/4/5, Ushiba)

  * SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

  * --(MN moving mass1)-- (2018/4/5, Ushiba)
  * --(MN moving mass2)-- (2018/4/5, Ushiba)
  * --(PF moving mass1)-- (2018/4/5, Ushiba)
  * --(PF moving mass2)-- (2018/4/5, Ushiba)
Line 190: Line 214:
  * --(MN, BFを用いたヒエラリカル制御 (TMのみなどではアクチュエータレンジ不足))-- (2018/1/14,牛場)   * MN, BFを用いたヒエラリカル制御 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

Check list for ETMX vacuum in spring, 2018

  • Term: ~2018/4/20

Schedule

  • 2018/3/26-4/6 : ETMX control test
  • 2018/4/9-12 : Closing EXC
  • 2018/4/5(Thur) 12:30 at fan hut.
  • 2018/4/11(Wed) 12:30 at fan hut.
  • 2018/4/12- : pump down
  • 2018/4/18-20: leak check


Each item should have following format;

  • item (checked date, checked person)

Once the item has been checked, it will be like:

  • item (2018/3/10, Somebody)


Alignment

  • Beam check at ETMX just before pump down(not possible with baffle PD through gate valve?) (2018/X/XX, Enomoto) -> Planned at 2018/4/11

  • Beam check at ETMY just before pump down (2018/X/XX, Enomoto) -> Planned at 2018/4/11

  • Beam check at REFL just before pump down (2018/X/XX, Enomoto) -> Planned at 2018/4/11

Preparation of monitors during pump down

  • Oplev monitor check for PRM (2018/X/XX Enomoto) -> Planned at 2018/4/11

  • Oplev monitor check for PR2 (2018/X/XX Enomoto) -> Planned at 2018/4/11

  • Oplev monitor check for PR3 (2018/X/XX Enomoto) -> Planned at 2018/4/11

  • Oplev monitor check for BS (2018/X/XX Enomoto) -> Planned at 2018/4/11

  • PD fot REFL (2018/4/XX Enomoto) -> Planned at 2018/4/11

  • GigE camera for IMMT1 (2018/X/XX Kokeyama) -> Planned at 2018/4/11

  • GigE camera for IMMT2 (2018/X/XX Kokeyama) -> Planned at 2018/4/11

  • GigE camera for PR2 (2018/X/XX Kokeyama) -> Planned at 2018/4/11

  • GigE camera for PR3 (2018/X/XX Kokeyama) -> Planned at 2018/4/11

  • GigE camera for BS (2018/X/XX Kokeyama) -> Planned at 2018/4/11

  • GigE camera for REFL (2018/X/XX Kokeyama) -> Planned at 2018/4/11

  • Tcam for ETMX (2018/4/11 Inoue)

  • Tcam for ETMY (2018/4/11 Inoue)

  • Tcam for ITMX (2018/4/5 Inoue)

  • Tcam for ITMY (2018/4/5 Inoue)

  • Illuminator for ETMX (2018/4/5 Yokozawa)

  • Illuminator for ETMY (2018/4/5 Inoue)

  • Vacuum gage for X end (2018/4/XX Inoue) -> Planned at 2018/4/16

  • Vacuum gage for X arm (2018/4/XX Inoue) -> Planned at 2018/4/16

  • Vacuum gage for Y arm (2018/4/XX Inoue) -> Planned at 2018/4/16

  • Vacuum gage for IXA arm (2018/4/XX Inoue) -> Planned at 2018/4/16

  • Vacuum gage for IYA arm (2018/4/XX Inoue) -> Planned at 2018/4/16

  • Vacuum gage for PRM-PR2 (2018/4/XX Inoue) -> Planned at 2018/4/16

  • 真空槽の傾きをdial gaugeで測る。 (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/13

  • Xend 機器制御 for status monitors (2018/4/XX Tomaru, Suzuki, Kimura) -> Planned at 2018/4/5, 6

  • Vacuum gauge monitor at the control room at least one location (2018/X/XX Uchiyama, Kimura, Inoue, Miyoki) -> Planned at 2018/4/XX

その他追加項目

  • EQ stopの隙間のチェック5mm程度 (2018/X/XX, Ushiba, Tomaru) -> (2018/4/11 planed)

  • 真空引き後、防振系の動作チェック (2018/X/XX, Enomoto) -> (2018/4/13 planed)

  • EXA ゲードバルブの動作チェック (2018/X/XX, Uchiyama) -> (2018/4/20 planed)

  • EXA ゲードバルブの開閉モニター to 機器制御 (今回は必須でないかもしれない) (2018/X/XX, Uchiyama) -> (2018/4/20 planed)

  • ダストウィットネスサンプル設置 (2018/X/XX, Hirose, Nakano) -> (2018/4/12 morning planed)

Type-A tower (高橋)

  • Fishing rodの動作チェック (2018/X/XX, Takahashi) -> (2018/4/6 planed, without camera)

  • Tuning of BF (2018/3/26, Takahashi)

  • Tuning of F3 (2018/3/27, Takahashi)

  • Tuning of TF (2018/3/27, Takahashi)

  • Tuning of position of BF damper (2018/3/28, Takahashi)

  • Centering IP (2018/3/27, Takahashi)

  • BF FRの動作確認 (2018/X/XX, Takahashi) -> (2018/X/XX planed)

  • BF yaw picomotorの動作確認 (2018/X/XX, Takahashi) -> (2018/X/XX planed)

  • トップ真空槽蓋閉め (2018/3/28, Takahashi)

  • トップ真空槽ボルト閉め (2018/X/XX, Kimura) -> (2018/4/10 planed)

  • クロス菅ボルト閉め (2018/X/XX, Kimura) -> (2018/4/10 planed)

  • IPの制御 (2018/4/XX, Okutomi) -> (2018/X/XX re-check)

  • BFのdamping制御 (2018/4/2, Okutomi) -> (2018/X/XX planed)

  • BF FRによるmirrorの高さ調整 (2018/4/5, Takahashi)

  • BF yaw picomotorによるmirrorのyaw調整 (2018/4/5, Ushiba)

  • 事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。 (2018/4/5, Ushiba)

  • BF温度計つなぎこみ (2018/X/XX, Takahashi, Ushiba) -> (2018/4/6 planed)

鏡板閉止 (Kimura)

  • 8K および 80Kシールドにつける窓類の取り付け (2018/4/xx, Ushiba) -> (2018/4/11 just before closing EXC door)

  • 輻射シールドのシャッター開確認 (2018/4/5, Ushiba)

  • 当該部のSuper Insulation(SI)取り外し確認 (2018/X/XX, Kimura) -> (2018/X/XX planed)

  • 鏡板取付前の変換フランジ取付 (2018/X/XX, Kimura) -> (2018/4/9 planed)

  • 鏡板取付後のビューポート取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed)

  • Oplev用の島取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed)

EXAチェンバー周り (Inoue)

  • フォトディテクターの取り外し (2018/3/26, Yokozawa)

  • GigEカメラの前の真空窓取り外しと取り付け (2018/X/XX, Inoue) -> (2018/4/9 planed)

EXV支持構造体のセット確認

  1. コーンベローズ用が固定されているかの確認 3箇所 (2018/4/9, 木村)
  2. チェンバー本体用 3箇所 <- 真空引き前にフリーにする 今回はやらない

真空引き開始前後 (木村)

  1. 真空フランジを開放し、再度閉止した箇所の確認(リーク試験箇所の確定に必要な情報です。)
    • グループ毎の申告による
      • EXA 鏡板閉止 (2018/4/XX, Kimura) -> (2018/4/10-12 planed)

      • EXV top flange: VIS group (2018/X/XX, Kimura) -> (2018/4/10-12 planed)

      • EXV ICF flange交換 ICF203/NW50 変換フランジ -> ICF203ブランクフランジ : VIS group (2018/3/28, Takahashi)

      • クロス菅鏡板2箇所: CRY group, VIS group (2018/X/XX, Kimura) -> (2018/4/10-12 planed)

      • ICF253送風機接続ポート: CRY group (2018/X/XX, , Kimura) -> (2018/4/10-12 planed)

      • EXC鏡板2箇所: CRY group (2018/X/XX, Kimura) -> (2018/4/11,12 planed)

      • EXC ViewPort 3箇所(鏡板1箇所、容器2箇所):AOS (2018/X/XX, Akutsu) -> (2018/4/12 planed)

      • 冷凍機NW-50フランジ交換 4箇所: CRY group (2018/X/XX, Kimura) -> (2018/4/10-12 planed)

      • EXA ICF152 2箇所: cal group (2018/4/5-6, Inoue) -> (2018/4/9 planed)

  2. 真空引き
    1. 真空計2台 ON (2018/X/XX, Kimura) -> (2018/4/13 planed)

    2. 粗挽きポンプスタート (2018/X/XX, Kimura) -> (2018/4/13 planed)

    3. 大まかなリークチェック (2018/X/XX, Kimura) -> (2018/4/13 planed)

    4. ターボポンプ冷却水循環装置スタート (2018/X/XX, Kimura) -> (2018/4/16 planed)

    5. ターボポンプスタート (2018/X/XX, Kimura) -> (2018/4/16 planed)

  3. リーク試験 (2018/4/XX, Kimura) -> (2018/4/18-20 planed)

    • (リーク判定 < 1x10-10 Pa・m3/s)

  4. ゲートバルブ動作試験 (2018/4/XX, Kimura) -> (2018/4/20 planed)

  5. (温度・圧縮機のモニター)
    • スタートさせる (2018/XX/XX, 都丸、麻生) -> (2018/X/XX planed)

    • 温度・圧縮機のループテスト (2018/XX/XX, 都丸、麻生、木村) -> 冷却開始前までに予定

Cryo payload (都丸、牛場)

  • リリース関係
    • PFのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)

    • MNのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)

    • MNRのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)

    • IMのリリース(6箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)

    • IMRのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)

    • TMのリリース(16箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)

    • TMRのリリース(15箇所) (2018/X/XX, Ushiba) -> (2018/4/12 planed)

  • センサーチェック
    • TM OpLev Pitch (2018/3/30, Ushiba, Tomaru)

    • TM OpLev Yaw (2018/3/30, Ushiba, Tomaru)

    • TM OpLev Length (2018/X/XX, Ushiba, Tomaru) -> (2018/4/16 planed)

    • IM PS H1 (2018/4/5, Ushiba)

    • IM PS H2 (2018/4/5, Ushiba)

    • IM PS H3 (2018/4/5, Ushiba)

    • IM PS V1 (2018/4/5, Ushiba)

    • IM PS V2 (2018/4/5, Ushiba)

    • IM PS V3 (2018/4/5, Ushiba)

    • MN PS H1 (2018/4/5, Ushiba)

    • MN PS H2 (2018/4/6, Ushiba)

    • MN PS H3 (2018/4/5, Ushiba)

    • MN PS V1 (2018/4/5, Ushiba)

    • MN PS V2 (2018/4/5, Ushiba)

    • MN PS V3 (2018/4/5, Ushiba)

    • MN OpLev Pitch (2018/X/XX, Miyamoto) -> (2018/4/12 planed)

    • MN OpLev Yaw (2018/X/XX, Miyamoto) -> (2018/4/12 planed)

    • 温度計A (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

    • 温度計B (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

    • 温度計C (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

    • 温度計D (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

    • 温度計E (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

    • 温度計F (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

    • 温度計G (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

    • 温度計H (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

  • アクチュエータチェック
    • TM アクチュエータ H1 (2018/4/5, Ushiba)

    • TM アクチュエータ H2 (2018/4/5, Ushiba)

    • TM アクチュエータ H3 (2018/4/5, Ushiba)

    • TM アクチュエータ H4 (2018/4/5, Ushiba)

    • IM アクチュエータ H1 (2018/4/5, Ushiba)

    • IM アクチュエータ H2 (2018/4/5, Ushiba)

    • IM アクチュエータ H3 (2018/4/5, Ushiba)

    • IM アクチュエータ V1 (2018/4/5, Ushiba)

    • IM アクチュエータ V2 (2018/4/5, Ushiba)

    • IM アクチュエータ V3 (2018/4/5, Ushiba)

    • MN アクチュエータ H1 (2018/4/5, Ushiba)

    • MN アクチュエータ H2 (2018/4/5, Ushiba)

    • MN アクチュエータ H3 (2018/4/5, Ushiba)

    • MN アクチュエータ V1 (2018/4/5, Ushiba)

    • MN アクチュエータ V2 (2018/4/5, Ushiba)

    • MN アクチュエータ V3 (2018/4/5, Ushiba)

    • SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)

    • MN moving mass1 (2018/4/5, Ushiba)

    • MN moving mass2 (2018/4/5, Ushiba)

    • PF moving mass1 (2018/4/5, Ushiba)

    • PF moving mass2 (2018/4/5, Ushiba)

  • ダンピング制御
    • MN, BFを用いたヒエラリカル制御 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)