Line 6: | Line 6: |
* Target: High power laser * Term: 2018/5/7 ~ 2018/9 === Stage 2 === |
|
Line 7: | Line 12: |
* Term: 2018/10 ~ 2018/12? | |
Line 13: | Line 19: |
* Term: 2018/5/7 ~ 2018/12? | |
Line 15: | Line 20: |
=== Stage 2 === | === Stage 3 === |
Line 17: | Line 22: |
* Term: 2018/12? ~ 2019/2? * Milestone |
|
Line 23: | Line 30: |
* Term: 2018/12? ~ 2019/2? | |
Line 25: | Line 31: |
=== Stage 3 === | === Stage 4 === |
bKAGRA Phase2
- Target: Joining O3 with ~10Mpc of BNC.
- Term: 2018/5/7 ~ 2019/May?
Stage 1
- Target: High power laser
- Term: 2018/5/7 ~ 2018/9
Stage 2
- Target: X arm commissioning
- Term: 2018/10 ~ 2018/12?
- Milestone
- VIS ITMX
- Initial alignment of X arm
- Cavity lock with IR
- Cavity lock with green
Stage 3
- Target: Y arm commissioning
- Term: 2018/12? ~ 2019/2?
- Milestone
- Replacing ETMY
- VIS and CRY of ITMY
- Initial alignment of Y arm
- Cavity lock with IR
- Cavity lock with green
Stage 4
- Target: FPMI commissioning
Stage 4
- Target: DRFPMI commissioning
Observation
- Joinning O3 of LIGO/VIRGO