2017/5/8 updated 2017/5/1 updated

bKAGRA Phase2

  • Target: Joining O3 with ~10Mpc of BNC.
  • Term: 2018/5/7 ~ 2019/May?


Schedule

2017/5/1 updated

KAGRA/Commissioning/Phase2/Chief180501_Phase2_schedule.png


Stage 1

  • Target: High power laser
  • Term: 2018/5/7 ~ 2018/9

Stage 2

  • Target: X arm commissioning
  • Term: 2018/10 ~ 2018/12?
  • Milestone
    • VIS ITMX
    • Initial alignment of X arm
    • Cavity lock with IR
    • Cavity lock with green

Stage 3

  • Target: Y arm commissioning
  • Term: 2018/12? ~ 2019/2?
  • Milestone
    • Replacing ETMY
    • VIS and CRY of ITMY
    • Initial alignment of Y arm
    • Cavity lock with IR
    • Cavity lock with green

Stage 4

  • Target: FPMI commissioning

Stage 4

  • Target: DRFPMI commissioning

Observation

  • Joinning O3 of LIGO/VIRGO