Differences between revisions 7 and 8
Revision 7 as of 2018-03-27 11:51:39
Size: 1762
Comment:
Revision 8 as of 2018-03-27 11:58:55
Size: 1743
Comment:
Deletions are marked like this. Additions are marked like this.
Line 52: Line 52:
 * Frequency noise can be measured by middle lock. Large intensity noise can be a problem.
Line 54: Line 55:
== 4. Phase2 ==
Line 57: Line 56:
 * Frequency noise can be measured by middle lock. Large intensity noise can be a problem.

Minute of KAGRA commissioning meeting


  • Date: 2018/3/27 11AM~12PM
  • Attendance: Miyakawa, Uchiyama, Yamamoto, Ohashi, Miyoki
    • eZuce: Kimura, Suzuki, Yokozawa, Inoue, Shoda, Ushiba, Tomaru


1. Report of work of the last week and plan of work

  • Alignment, ETMY: Izumi
    • Mirror motion has been suppressed to ~2urad. Requirement is 1urad.
    • Beam is checked almost every night.
  • MIF: Izumi
    • k1bs, k1imc will be connected by Dolphin. ETMs are connected to k1imc by RFM.
  • CAL: Yamamoto, Yokozawa
    • Started using IMC as training of calibration.
      • Simple calibration will be implemented.
    • X end PD is removed at 3/27 today.
  • ETMX:
    • Connection between Type A and Cryopayload is done. Cabling is done.
    • Height somehow changed from the last week to this week. We are fixing it, but it seems to change daily.
    • Alignment will be roughly adjusted today, and first contact will be removed today.
    • Circuits and connection to digital system are done. We started matrix tuning.
    • Viewport of Oplev is missing. It will be placed the next, but we need indium.

2. ETMX pump-down

  • See the check list.

3. Operation

  • Please reply accommodation mail from Uchiyama-san.
  • Think for emergency.

4. Tasks or discussions

  • Selection of full channel -> DGS Yamamoto

  • Selection of science channel -> Commissioning Izumi

  • Screens at control room
    • Sensitivity.
    • PEM.
    • Needs laser safety information.
  • GW alert: online alert in the control room might be prepared. -> Togoshi

  • Frequency noise can be measured by middle lock. Large intensity noise can be a problem.

Others

  • Next meeting: 3/27

KAGRA/Commissioning/Weekly/20180327/Minute (last edited 2018-03-27 11:59:37 by OsamuMiyakawa)