Minute of KAGRA commissioning meeting


  • Date: 2018/4/10 11AM~12PM
  • Attendance: Uchiyama, Aso, Miyakawa
    • eZuce: Kimura


1. Report of work of the last week and plan of work

  • IFO: Enomono
    • Michelson fringe could be seen yesterday!
  • ETMs: Ushiba
  • RT model
    • Yamamoto-kun found how to start/stop Dolphin without killing RT models connected to Dolphin.
    • BS model was splitted into 4kHz and 16kHz. No glitch was seen since then.
  • CAL: Yamamoto, Yokozawa
    • RT calibration using IMC as training of calibration will be tested soon.
    • Off line calibration using FIR filter won't be used in phase 1.
  • DAQ
    • Recoding minute_raw of k1fw0 moved to SSD at k1tw0.

2. Emergency call list

3. Operation

  • How to request the engineering things was announced.
    • Contact Hayakawa or Ohashi for facility, Awai or Miyoki for electric power, Tomura or Miyakawa for circuits.

4. Tasks or discussions

  • DAQ fix -> Miyakawa, Yamamoto

  • Selection of full channel -> DGS Yamamoto

  • Selection of science channel -> Commissioning Izumi

  • Screens at control room
    • Sensitivity.
    • PEM.
    • Needs laser safety information.
  • GW alert: online alert in the control room might be prepared. -> Togoshi

Others

  • Dust monitor using sapphire disk will be implemented around 4/10.
  • Phase 1 summarize should talk wide range view.
    • Type A has double stable point.
    • Monitor for water level, and vacuum gage for weekend should be implemented.
    • Patrol light should be implemented soon, even manual one.
  • Gardian of TYPE A must be implemented and tested.
  • Pump down meeting meeting at Fan hut: 12:30 at 4/5, 12:30 at 4/11
  • Next meeting: 4/10