Minute of KAGRA commissioning meeting


  • Date: 2018/4/17 11AM~12PM
  • Attendance: Miyakawa, Kokeyama, Aso, Uchiyama, Miyoki, Akutsu
    • eZuce: Yamamoto, Suzuki


1. Report of work of the last week and plan of work

  • VAC:
    • Door was closed and pump down started. One large leak was found and it being searched where it is.
  • IFO, ETMs: Enomono, Ushiba
    • Michelson fringe was seen on DC and RF, but still mirror motion is too large.
    • Needs more work for damping for both ETMs.
  • DGS:
    • IO chassis of k1ioo was disconnected somehow. It is being checked now.
  • DAQ
    • Recoding minute_raw of k1fw1 moved to SSD at k1tw1. All fw0,1 tw0,1 are working well without any gap on data.

2. Operation

  • Noise injection needs some preparations for speakers.
  • Schnupp asymmetry need some preparations.
  • Other plan seems to be ready.
  • CBC will perform an online analysis.

3. Tasks or discussions

  • Selection of full channel -> DGS Yamamoto

  • Selection of science channel -> Commissioning Izumi

  • Screens at control room
    • Sensitivity.
    • PEM.
    • Needs laser safety information.
  • GW alert: online alert in the control room might be prepared. -> Togoshi

Others

  • Phase 1 summarize should talk wide range view.
    • Type A has double stable point.
    • Monitor for water level, and vacuum gage for weekend should be implemented.
    • Patrol light should be implemented soon, even manual one.
  • Next meeting: 4/10

KAGRA/Commissioning/Weekly/20180417/Minute (last edited 2018-04-17 11:19:38 by OsamuMiyakawa)