Differences between revisions 4 and 6 (spanning 2 versions)
Revision 4 as of 2018-06-19 11:39:43
Size: 2199
Comment:
Revision 6 as of 2018-06-19 11:44:01
Size: 1322
Comment:
Deletions are marked like this. Additions are marked like this.
Line 39: Line 39:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5224]]
Line 40: Line 41:

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5224]]
  * ring on f0 got lower and on the f1 by a few mm.
  * f0 TF had no response. Line to coil was cut. It had been repaired before and it was used again.
  * It will be fixed around September as 1week work. Whole coil will be replaced.

== X arm commissioning/preparation ==
 * WFS target: 10nrad.
 *

== Satellite box modification ==
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0083/G1808352/001/G1808352_v1.pdf]]
 * 100nF cap will be implemented to avoid an oscillation. It introduce 41Hz pole.

== MC realignment ==
 * MC will be re-aligned today.

== FSS BO ==
 * BO card was broken and it was replaced.
 * BO check card is still connected between BO card and circuit to break ground loop.

== PMC installation, circuits, adding offset ==
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5227]]
 * Trying to implement an offset using slow output into EXC.
Line 68: Line 45:
 * Next meeting: 6/19.  * Next meeting: 6/26.

Minute of KAGRA commissioning meeting


  • Date: 2018/6/19 11AM~12PM
  • Attendance: Miyakawa, Aso, Yokozawa, Ohishi, Kokeyama, Miyoki, Tahara, Enomoto, Stefan, Tomura, Ushiyama, Nakano
    • eZuce: Ushiba, Izumi, Inoue, Yamamoto(Toyama), Suzuki, Hirose, Shoda


0. Schedule

  • k1ix0 will be needed by September for NAB PD.

Laser

  • Transmissivity of Faraday Isolator suddenly reduced 60% to 40%.
  • Starding Fiber amp failed due to too low power at the sensor.
  • We will use spare at Mio labs. We can use current low power laser, so schedule won't be changed so much.

IMMT

  • Changed titanium screws.
  • IMMT1 repare was done, with 1cm position accuracy.
    • 1cm is not enough(Izumi).
  • IMMT2 repare will be held 7/9~.

PMC

  • Offset was implemented.
  • Whitening will be implemented by daughter board.
    • Needs gain at low frequency in digital loop.

Useful scripts for RT-models

Others

  • Next meeting: 6/26.