Minute of KAGRA commissioning meeting


  • Date: 2018/6/26 11AM~12PM
  • Attendance: Miyakawa, Yokozawa, Stefan, Nakano, Yamamoto
    • eZuce: Shoda, Ushiba, Hirose, Eleonora, Izumi, Yamamoto(Toyama), Kokeyama


PMC

Others

  • Beam height brain storming -> next week?

  • Necessary number of High power coil driver -> Aso

  • Next meeting: 7/3.

KAGRA/Commissioning/Weekly/20180626/Minute (last edited 2018-06-26 11:48:50 by OsamuMiyakawa)