Line 24: Line 24:
 * 5m fiber noise was measured and fitted, and will be scaled to 50m longer.
Line 29: Line 30:
 * Circuit inside of pre-ampifier seems to be something wrong.
 * LED light can be a noise. (Miyoki)
 * Long cable could be noise, but after changing did not fix.
 * Current monitor of HPCD can oscillate easily. At the coil output, no noise increment, no strange transfer function can be seen, but we did not check offset jump. We should do.
Line 38: Line 42:
 * pile of AA or HPCD can be hot.
Line 41: Line 46:
 * Necessary number of High power coil driver -> Aso  * Necessary number of High power coil driver -> Aso -> Current number of HPCD including 16 spares seems to be enough.
Line 45: Line 50:
  * Where is an actual beam hight? -> 30urad * ~10m -> not a big amount.
  * Effect of window of gate valve?

Minute of KAGRA commissioning meeting


  • Date: 2018/7/3 11AM~12PM
  • Attendance: Miyakawa, Aso, Miyoki, Enomonoto, Yokozawa
    • eZuce: Suzuki, Shoda, Hirose, Izumi, Yamamoto(Toyama), Ohashi, Kimura, Tomaru, Inoue


LAS

ALS

VIS

  • Geophone Noise Hunting -> Tanioka

  • Circuit inside of pre-ampifier seems to be something wrong.
  • LED light can be a noise. (Miyoki)
  • Long cable could be noise, but after changing did not fix.
  • Current monitor of HPCD can oscillate easily. At the coil output, no noise increment, no strange transfer function can be seen, but we did not check offset jump. We should do.

AOS

rack cleaning

  • Cable cleaning on BS rack will be done this weekend.
  • pile of AA or HPCD can be hot.

Others

  • Necessary number of High power coil driver -> Aso -> Current number of HPCD including 16 spares seems to be enough.

  • NAB PD cabling -> Aso

  • Beam height brain storming
    • ETMX and ITMX should be located at half low temperature stage and room temperature stage. It means that ~5mm off from the nominal position. Type A can compensate ~5mm.
    • Where is an actual beam hight? -> 30urad * ~10m -> not a big amount.

    • Effect of window of gate valve?

Others

  • Next meeting: 7/17.