== 2018/8/28 Commissioning meeting topics == * Daily meeting * Night work * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8720|JGW-E1808720]] * Task check for IXC installation and closing to vacuum * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX|Check list]] * Readiness for the X arm commissioning. * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]] * Initial alignment * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8462|JGW-G1808462]] ---- * Laser, PSL, IOO report * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5892]]: PMC * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5894]]: FSS * ETMX damping * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5899]] * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5906]] * Satellite amplifier * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8691|JGW-T1808691]]: TF at low frequency has 30db bump. * DGS * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5887]] * Magnetic field measurement at IXC * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5817]]