=== Schedule ===
Line 12: Line 14:
 * 11/16: AM or PM for 30min : Inspection for ETMX cleaning
 * 11/26~12/9 Daytime: Y arm alignment from BS to ETMY: Enomoto, Miyazaki, Yokogawa, Sugimoto
  * Needs help for Y arm alignment
 * 11/16: PM for 30min : Inspection for ETMX cleaning
 * Needs time sharing with MZ in the daytime until 11/26.

 * 11/26~12/9 Daytime: Y arm alignment from BS to ETMY using IR beam.
  * Members
: Enomoto, Miyazaki, Yokogawa, Sugimoto
  * Beam alignment actually starts after the installation of NAB. It will take several days.
  * Green from SR2 will be available after 12/9.
  * Need
s help for Y arm alignment.
Line 18: Line 24:
=== Discussion ===

2018/11/13 Commissioning meeting topics


Schedule

  • Every Wednesday morning: Maintenance
  • 11/5-end of Nov.: Route to IYA is closed.
  • 11/16: PM for 30min : Inspection for ETMX cleaning
  • Needs time sharing with MZ in the daytime until 11/26.
  • 11/26~12/9 Daytime: Y arm alignment from BS to ETMY using IR beam.
    • Members: Enomoto, Miyazaki, Yokogawa, Sugimoto
    • Beam alignment actually starts after the installation of NAB. It will take several days.
    • Green from SR2 will be available after 12/9.
    • Needs help for Y arm alignment.
  • 12/10 or 11: ETMX cleaning


Discussion

  • We learned we need to monitor VIS motion when pump down. We may need also some monitors VIS motion when venting.


KAGRA/Commissioning/Weekly/20181113/Agenda (last edited 2018-11-13 10:31:13 by OsamuMiyakawa)