 * Needs re-scheduling for the X arm commissionig?

2018/11/20 Commissioning meeting topics


Schedule

  • Every Wednesday morning: Maintenance
  • 11/5-end of Nov.: Route to IYA is closed.
  • 11/16: PM for 30min : Inspection for ETMX cleaning
  • Needs time sharing with MZ in the daytime until 11/26.
  • 11/26~12/9 Daytime: Y arm alignment from BS to ETMY using IR beam.
    • Members: Enomoto, Miyazaki, Yokogawa, Sugimoto
    • Beam alignment actually starts after the installation of NAB. It will take several days.
    • Green from SR2 will be available after 12/9.
    • Needs help for Y arm alignment.
  • 12/10 or 11: ETMX cleaning


Discussion

  • We learned we need to monitor VIS motion when pump down. We may need also some monitors VIS motion when venting.
  • Needs re-scheduling for the X arm commissionig?