 * Date: 2018/11/27 11AM~12PM
 * Attendance: Miyakawa, Aso, Enomoto, Izumi, Lucia
  * Zoom: Kozakai, Yamamoto, Koseyama, Oshino, Suzuki, Yokozawa, Ushiba
 * Date: 2018/11/27 11:15AM~12PM
 * Attendance: Miyakawa, Aso, Nakano, Akutsu, Oshino, Kokeyama
  * Zoom: T.Yamamoto, Yokozawa, Ushiba, Miyoki, Uchiyama
Line 10: Line 10:
 * CAL injection on 11/26-29 won't affect to commissioning task.  * ITMY alignment needs opening chamber.
 * Green will be available in January after all.
Line 14: Line 15:
 * We need 2weeks more.
 * Minimum success is stabilization of IR fluctuation to cavity resonant frequency.
 * We had 1 month more until 1/6.
 * BS is sitting and fixed, but some of the motor and OSEM are available. It seems to be ok for the Y arm alignment.
Line 20: Line 20:
  * 2hours lock was lost not by instability of VIS, by something but we are not sure.
  * IR flashes could be seen with CARM lock, but it is not sure it was TEM00. We could know FSR of cavity by the measurement.
Line 24: Line 22:
  * Nakano-kun, Eleonora lead the Y arm commissioning task, and Sugimoto-kun can join to Y arm team. Enzo and Type B team can work for commissioning work specially for BS and SR.
Line 28: Line 25:
  * Characterization for PMC, IMC, FSS started. The results will be summerized to somewhere.
  * ISS noise hunting started. No difference was seen between KIKUSUI and KEPCO DC power supply.
Line 34: Line 29:
 * Next meeting: 11/27.  * Next meeting: 12/4.

Minute of KAGRA commissioning meeting


  • Date: 2018/11/27 11:15AM~12PM
  • Attendance: Miyakawa, Aso, Nakano, Akutsu, Oshino, Kokeyama
    • Zoom: T.Yamamoto, Yokozawa, Ushiba, Miyoki, Uchiyama


Schedule

  • ITMY alignment needs opening chamber.
  • Green will be available in January after all.

Discussion

  • We had 1 month more until 1/6.
  • BS is sitting and fixed, but some of the motor and OSEM are available. It seems to be ok for the Y arm alignment.


  • X arm lock
  • Yarm commissioning
  • Laser, PSL, IOO report

Others

  • Next meeting: 12/4.