2018/12/4 Commissioning meeting topics


Schedule

  • Every Wednesday morning: Maintenance
  • 11/5-end of Nov.: Route to IYA is closed.
  • 12/10 or 11: ETMX cleaning
  • Week of 12/10: Night work ok.
  • Week of 12/17~: No night work.
  • New schedule Plan B is proposed. Other list by Saito.

    • Extended date: 12/10-1/6.
    • 1/6: End of X arm commissioning -> Open chambers.

    • Week of 1/7~: no beam in the daytime
    • 1/18~ : Y arm alignment from BS to ETMY using IR beam.
    • 2/18~ Y arm commissioning


Discussion

  • We learned we need to monitor VIS motion when pump down. We may need also some monitors VIS motion when venting.