 * Time sharing without night work time in the mine, specially CAL, VIS and commissioning.
  * 12/18-28: CAL work at EXA
Line 48: Line 46:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7425]]: ALS noise investigation: ADC noise and re-measurement of VCO noise
Line 51: Line 48:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7451]]: Installation of High power beam shutter
Line 54: Line 50:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7469]]: Evacuating the EXT chamber

2019/1/8 Commissioning meeting topics


Schedule

  • 1/4 Camera moves to ETMY.
  • 1/6: End of X arm commissioning.
  • 1/7: Removal of aluminum foil for WAB at EYC.
    • 1/7?: Removal of first contact of ETMY
  • 1/7~ : Opening chambers.
    • 1/7~ : High power beam dump installation.
    • 1/14~18 : Hight check for VIS systems.
    • 1/7~11 : BS tuning
  • 1/9: EYC pumping down
  • beam alignment:
    • 1/7~: Opening IMC Chamber.
      • IMC beam alignment in air: 1/11-14
      • IMC lock recover in vacuum: 1/16
      • IMC to ETMX: 1/17-21
    • BS to ETMY: 1/17-21
    • ITMY to REFL: 1/21-22
    • ITMY to SRM: 1/22-23
    • ITMY to OMC: 1/23-25
    • ITMX to OMC: 1/23-25
    • POS to ETMY(Green laser): 1/23-24
    • ETMY to POS(Green laser): 1/24-25
    • ETMX to ITMX: 2/11-22
  • 2/4~ DRMI Y arm commissioning
  • 2/18~ Y arm commissioning
  • 3/18~ FPMI commissioning


Discussion


  • X commissioning
  • Laser, PSL, IOO report
  • AOS