Line 28: Line 28:
  * ITMY to REFL: 1/21-22
  * ITMY to SRM: 1/22-23
  * ITMY to OMC: 1/23-25
  * ITMX to OMC: 1/23-25
  * ITMY to REFL: 1/21-22
   * ITMY to SRM: 1/22-23
  * ITMY to OMC: 1/23-25
   * ITMX to OMC: 1/23-25
Line 33: Line 33:
  * ETMY to POS(Green laser): 1/24-25
  * 1/27: end of alignment up to SRs
  * ETMX to ITMX: 2/21-22
  * ETMY to POS(Green laser): 1/24-25
  * '''1/27: end of alignment up to SRs'''
Line 37: Line 36:
 * Yend PCal Finalinization 1/25-2/22
 * Yend WAB 2/25-3/4
 * Yend pumpdown 3/8~
  * leak test 3/11,12
 * Night work start: 3/11~
  * 2/18-20 EXC door close
   * ETMX to ITMX: 2/21-22
Line 43: Line 39:
 * 2/4(no delay)-3/8 DRMI Y arm commissioning
 * 3/11(3weeks delay)-4/5 Y arm commissioning
 * 3/25(1week delay) ~ FPMI commissioning
 * Yend
  * 1/25-2/22: Yend Pcal finalization
  * 2/25-3/4: Yend WAB
  * 3/8~ : Yend pumpdown 3/8~
   * 3/11,12: leak test

 * Xend
  * 2/22-3/10: Xend Pcal finalization
  * 2/11-2/22: Xend NAB installation
  * 3/11- Xend WAB
Line 48: Line 51:
 *  * 3/11~ : Night work start
Line 50: Line 53:
 * 2/18~ Y arm commissioning  * 2/4(no delay)-3/8 DRMI commissioning
 * 3/11(3weeks delay)-4/5 Y arm commissioning
 * 3/25(1week delay)-4/5 FPMI commissioning

2019/1/8 Commissioning meeting topics


Schedule

  • 1/4 Camera moves to ETMY.
  • 1/6: End of X arm commissioning.
  • 1/7-15: Laser stop in the laboratory area.
  • 1/7: Removal of aluminum foil for WAB at EYC.
    • 1/7?: Removal of first contact of ETMY
  • 1/7~ : Opening chambers.
    • 1/7~ : High power beam dump installation.
    • 1/14~18 : Hight check for VIS systems.
    • 1/7~11 : BS tuning
  • 1/9? or later: EYC pumping down
  • beam alignment:
    • 1/7~: Opening IMC Chamber.
      • IMC beam alignment in air: 1/11-14
      • IMC lock recover in vacuum: 1/16
      • IMC to ETMX: 1/17-21
    • BS to ETMY: 1/17-21
      • ITMY to REFL: 1/21-22
      • ITMY to SRM: 1/22-23
      • ITMY to OMC: 1/23-25
      • ITMX to OMC: 1/23-25
    • POS to ETMY(Green laser): 1/23-24
      • ETMY to POS(Green laser): 1/24-25
    • 1/27: end of alignment up to SRs

    • 2/18-20 EXC door close
      • ETMX to ITMX: 2/21-22
  • Yend
    • 1/25-2/22: Yend Pcal finalization
    • 2/25-3/4: Yend WAB
    • 3/8~ : Yend pumpdown 3/8~
      • 3/11,12: leak test
  • Xend
    • 2/22-3/10: Xend Pcal finalization
    • 2/11-2/22: Xend NAB installation
    • 3/11- Xend WAB
  • 3/11~ : Night work start
  • 2/4(no delay)-3/8 DRMI commissioning
  • 3/11(3weeks delay)-4/5 Y arm commissioning
  • 3/25(1week delay)-4/5 FPMI commissioning


Discussion

  • X amr commissioning summary
  • schedule for Y arm alignment, etc.
  • Modulation by Mach-Zehnder