== 2019/1/22 Commissioning meeting topics == * Assignment of staffs for night work * [[https://teamup.com/kswnmta8p18h6u1uab]] * Readiness for the X arm commissioning. * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]] ---- === Schedule === * beam alignment: * 1/7~: Opening IMC Chamber. * IMC beam alignment in air: 1/11-14 * IMC lock recover in vacuum: 1/16 * IMC to ETMX: 1/17-21 * BS to ETMY: 1/17-21 * ITMY to REFL: 1/21-22 * ITMY to SRM: 1/22-23 * ITMY to OMC: 1/23-25 * ITMX to OMC: 1/23-25 * POS to ETMY(Green laser): 1/23-24 * ETMY to POS(Green laser): 1/24-25 * '''1/27: end of alignment up to SRs''' * 2/18-20 EXC door close * ETMX to ITMX: 2/21-22 * Yend * 1/25-2/22: Yend Pcal finalization * 2/25-3/4: Yend WAB * 3/8~ : Yend pumpdown 3/8~ * 3/11,12: leak test * Xend * 2/22-3/10: Xend Pcal finalization * 2/11-2/22: Xend NAB installation * Periscope installation * 3/11,12 Xend WAB * 3/19,20, Heatlink etc. * 3/22 Pumping down * Leak test * 3/11~ : Night work start * 2/4(no delay)-3/8 DRMI commissioning * 3/11(3weeks delay)-4/5 Y arm commissioning * 3/25(1week delay)-4/5 FPMI commissioning ---- === Discussion === * X amr commissioning summary * schedule for Y arm alignment, etc. * Modulation by Mach-Zehnder ----