2019/3/26 Commissioning meeting topics


Schedule

  • Center
    • 2/26-27: Venting

    • 2/28-3/15: Health check and maintenance for VIS
      • PRM: One flag was dropped. -> leave it

      • 3/4-14 PRM: Misalignment does not reach where beam hits damper.

      • 3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.

      • 3/15: BS: Yaw offset adjustment by hand. -> 3/5-6

        • 3/12: BS ok

      • 3/15: some SRs work

    • 3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.

    • 3/18: Re-alignment

    • 3/19-21: Closing

    • 3/22: Pump down

    • 3/25: Venting

    • 3/27: Fixing PR2
    • 4/3: Closing and pump down
  • ITMX:
    • 3/19: Cooling stop

    • 3/25: Venting start
    • 3/27: Opning chamber
    • 3/27~: Fixing thermal touch
    • ~4/3: closing chamber and start pumping down.
    • 4/12: Cooling starts.
  • Xend
    • 2/11-2/14: Xend NAB installation

    • 2/21: Removing FC, Payload release

      • 2/27: ETMX release

    • 2/23-3/6: Xend Pcal finalization 1

      • Periscope installation

      • 3/6: Beam position by IR and Green

    • 3/5 AOS: EY and EX(if they have time) work.

    • 3/6: Green X alignment (no IR), and no hazard at Y end.

    • 3/11, ~20: Xend WAB finalization.

    • 3/11~3/15: ETMX tuning.

    • 3/19: ETMX finalization by Takahashi

    • 3/18,19: ETMX alignement

    • 3/23-24: Pcal alignment

    • 3/24: Removing PD

    • 3/25: closing and pump down
    • 4/12: Cooling start
  • Yend
    • 1/25-2/20: Yend Pcal finalization

    • 3/5: EYA remaining works by Enomoto, Inoue.

    • 2/25-3/5: Yend WAB finalization

    • 3/6: Y end closing (no laser hazard at least in the morning)

    • 3/7: Y end pump down

    • 3/22-23: leak test

    • 3/26: Venting start
    • 3/28~: Fixing short inside chamber
    • ~4/2: closing chamber and start pumping down.
    • 4/10: Cooling starts.
  • 4/1~ : Night work starts, daily meeting will be moved to 1PM
    • Summary of work will last for a while in the morning meeting.
  • 2/18-2/22: PRMI commissioning

  • End of April~: DRMI commissioning
  • End of April~: Y arm commissioning
  • ~End of May: FPMI commissioning


Discussion

  • Schedule estimation for commissioning with feedback to ITMY.
    • 4/10: ETMY cooling start
    • 5/7: ETMY cooling done
    • 3/29: ITMY cooling done
    • 4/1-4/26: ITMY TF measurement for hierarchy control 2.
    • 4/1-4/26: ITMY payload matrix diagonalize
    • 5/7-5/10 Y arm lock with mass feedback to ITMY
    • 4/12: ETMX, ITMX cooling start
    • 5/9: ETMX, ITMX cooling done
    • 5/7-5/10 X arm lock with green light
    • 5/13-17: FPMI lock
    • when both ends are not available: DRMI lock acquisition. It will be continued after FPMI is locked.
  • Strategy for TF measurement and payload diagonalization.
  • There is a possibility that ITMY is not going low temperature.
  • When should we start daily meeting?
  • IOO will use iMC before starting Y arm commissioning.
  • How to avoid troubles?


KAGRA/Commissioning/Weekly/20190326/Agenda (last edited 2019-03-26 10:56:35 by OsamuMiyakawa)