Minute of KAGRA commissioning meeting


  • Date: 2019/3/26 11:00AM~12PM
  • Attendance: Miyakawa, Nakano, Oshino, Yong-min, Aso, Yamamoto, Enomoto.
    • Zoom: Takahashi, Sawada, Koseyama, Tomaru


Discussion

  • It is better to have cavity when TF measurement is performed.
    • ETMY cooling will start 4/10. We start some test during cooling, maybe 1 week or 2weeks after starting.
  • Simple red/green status monitor is necessary.
  • Responsible person should be assigned in subgroup. -> ask chief to assign responsible persons for each task (ex. Type A, Type B...)


Others

  • Next meeting: 4/2 discussion for Type A strategy.

KAGRA/Commissioning/Weekly/20190326/Minute (last edited 2019-03-26 13:00:07 by OsamuMiyakawa)