Line 41: Line 41:
  * 4/22: Cooling start   * 4/22: vent
  * 4/24: fix oplev mirror
  * 4/25: Pumpdown
  * 5/2: leak check
  * 5/2: Cooling start
Line 57: Line 61:
 * Report for ITMY status.
Line 59: Line 62:
 * Report for ITMY status for TF measurement and matrix diagonalization.
 * Y arm lock trial.
 * Towards the FPMI lock.

2019/4/23 Weekly commissioning meeting topics



Schedule

Schedule

  • Center
    • 3/25: Venting

    • 3/27-4/9: Fixing PR2 or others

      • 4/4 -4/5: Gluing

      • 4/8: alignment check

      • 4/8-10: OSEM adjustment

    • 4/10: alignment check

    • 4/11: VIS final health check

    • 4/11-12: Closing

    • 4/12: Pump down

    • 4/29,30: Leak check
  • ITMX:
    • 3/19: Cooling stop

    • 3/25: Venting start

    • 3/27: Opning chamber

    • 3/27~: Fixing thermal touch

    • 4/2~: closing chamber and start pumping down

    • 4/10: Cooling starts.

  • Xend
    • 3/25: closing and pump down

    • 4/8: Leak check

    • 4/9-10: venting

    • 4/11: Exchange a broken LED for Photo sensor

    • 4/12: closing chamber and start pumping down

    • 4/22: Leak check
    • 4/22: vent
    • 4/24: fix oplev mirror
    • 4/25: Pumpdown
    • 5/2: leak check
    • 5/2: Cooling start
  • Yend
    • 3/26: Venting start

    • 3/28~: Fixing short inside chamber

    • 4/3: Fixing F0 actuator

    • 4/4~: closing chamber and start pumping down.

    • 4/10: Cooling starts.

  • April: Measurement of TF, payload diagonalization on ITMX
  • End of April~: DRMI commissioning
  • End of April~: Y arm commissioning
  • ~End of May: FPMI commissioning


Discussion

  • Report for ITMY status for TF measurement and matrix diagonalization.
  • Y arm lock trial.
  • Towards the FPMI lock.