2019/5/14 Weekly commissioning meeting topics


Schedule

  • Xend
    • 5/2: Cooling start

    • 5/29 cooling will be done.
  • 5/12-13: Height adjustment for ITMX and ITMY.
  • 5/14: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS, )

  • ~5/17: Y arm lock trial.
  • 5/20-24: Exchanging cryo valves.
  • ~End of May (might be delayed to middle of June?): Y arm, FPMI commissioning
    • Measurement of TF, payload diagonalization on ITMX


Discussion

  • Strategy for height difference between ITMX and ITMY.
  • Status of Y arm lock trial.
    • Feed back to ETMY?