== 2019/7/2 11:00-12:00 Weekly commissioning meeting topics == * Zoom URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]] * Assignment of staffs * [[https://teamup.com/kswnmta8p18h6u1uab]] ---- ==== Schedule ==== * --(6/18 Move PR3)-- * 6/19: DRMI locked. * 6/21: polarization issue found. * ITMX * ETMX * 6/21: Stop cooler. * ITMY * Inject Nitrogen * 7/2?: pump down again * ETMY * 6/20: Stop cooler * 6/28: Open chamber and fix alignment * 7/2: Closing chamber and start pump down * Long term: * --(4/22-5/31: Yarm commissioning)-- * --(5/27-6/30: DRMI commissioning)-- * 7/1-8/9: FPMI/DRFPMI commissioning * 8/12-10/4: ASC * 10/7-11/15: Post Commissioning * 11/18-12/13: Noise hunting ---- === Discussion === * Engineering run * Hours * IFO configuration * missing items ---- Trigger rate during ER [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10368|slides]]