Minute of KAGRA commissioning meeting


  • Date: 2019/7/2 11:00~12:00
  • Attendance: Miyakawa, Koseyama, Aso, Nakano, Kozakai, Fabian, Miyoki, Takahashi, Akutsu, Inoue, Miyo, Washima, Ogaki, T. Yamamoto
  • Zoom: Hiro Yamamoto, Ohashi, Uchiyama, Eleonora, Mio, Ushiba


Summary of last week

  • ETMY misalignment was fixed.
  • Investigation of polarization is going on.
  • We keep central area for a while and keep DRMI characterization specially for control.
  • We confirmed that we would have an engineering run on 7/13.

Discussion

  • 12pm-6pm
    • PEM needs ~10min after run.
    • CAL needs free swinging Michelson.
  • Michelson
  • Action items for this month
    • Investigation for shape of reflection of both ITEX and ITMY.
      • P-pol shape with PRMI lock.
      • Rotating polarization of geen.
    • Control signal for PRMI/DRMI with polarization.
      • Education for DRMI from specialty.
    • Y arm lock with mass lock.
    • FPMI lock.
      • noise hunting.
    • Dampin test mass.


Others

  • Next meeting: 7/2.