Line 23: Line 23:
  * --(4/22-5/31: Yarm commissioning)--
  * --(5/27-6/30: DRMI commissioning)--

2019/7/16 11:00-12:00 Weekly commissioning meeting topics


Schedule

  • ~7/31: Trial for DRMI with polarization.
  • 7/6~: Trial for mass lock
  • ITMX
  • ETMX
  • ITMY
  • ETMY
  • Long term:
    • 7/1-8/9: FPMI/DRFPMI commissioning
    • 8/12-10/4: ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting


Discussion

  • Status of FPMI
  • DRFPMI plan
  • Fiber noise cancellation