Line 3: Line 3:
 * Time :''' From 2019/Dec/17(09:00) to 2019/Dec/24(09:00)'''  * Time :''' From 2019/Dec/17(17:00) to 2019/Dec/24(09:00)'''
Line 5: Line 5:
 * Rough Schedule

 || Dec/10-16(09:00) || Commissioning and preparation ||
 || Dec/16(Mon,09:00)~17/(Tue,17:00) || Concentrate longer stable operation of FPMI ||
 || Dec/17(Tue, 17:00) || start ||
 || Dec/24(Tue, 09:00) || end ||
 || Dec/24(Tue, 09:00 ~ (17:00) ) || proposed post ER tasks ||

----
=== For shifts ===
 * [[KAGRA/EngineeringRun/ER191217_24/Shift|Collaborator shift manuals]]

----


Line 6: Line 22:
  * [[ |MIF]]   * [[KAGRA/EngineeringRun/ER191217_24/IFO|IFO(IOO, MIF.LAS)]]
Line 8: Line 24:
  * [[ |PEM]]   * [[KAGRA/EngineeringRun/ER191217_24/PEM|PEM]]
Line 11: Line 27:
  * [[ |DetChar]]
  * [[ |VIS]]
  * [[KAGRA/EngineeringRun/ER191217_24/DetChar|DetChar]]
  * [[KAGRA/EngineeringRun/ER191217_24/VIS|VIS]]
Line 15: Line 31:
  * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/EngineeringRun/ER191217_23/FCL|FCL]]   * [[JGWwiki/KAGRA/EngineeringRun/ER191217_24/FCL|FCL]]
Line 17: Line 33:
  * [[ |Special for LV ? ]]   * [[KAGRA/EngineeringRun/ER191217_24/forLV |Special for LV and O3]]
  * [[KAGRA/EngineeringRun/ER191217_24/postERtrial| Post ER trial plans]]
Line 19: Line 36:
 * [[ |Shift]]

ER191217~191224

  • Time : From 2019/Dec/17(17:00) to 2019/Dec/24(09:00)

  • JRPC Discussions on 5th December

  • Rough Schedule

    Dec/10-16(09:00)

    Commissioning and preparation

    Dec/16(Mon,09:00)~17/(Tue,17:00)

    Concentrate longer stable operation of FPMI

    Dec/17(Tue, 17:00)

    start

    Dec/24(Tue, 09:00)

    end

    Dec/24(Tue, 09:00 ~ (17:00) )

    proposed post ER tasks


For shifts