Line 10: Line 10:
 * Detach white tapes and release the cables.
 * Connect the cables to flanges.
Line 12: Line 14:
 * Check the signal integrity
  * To do so, the hanged table should move slightly.
  * But never jump to it, as we need to install the BRT on TMS-VIS; we need rather a rigid stage when we torque screws to fix BRT to TMS-VIS.
  * So, Uraguchi-san suggested the procedure. It should be docuented later. It is a little bit complicated about the dummy weights and restraints and new shims.

20180926

Today's activities

Workers: Akutsu, Uraguchi, K. Nagano, Hasegawa, T. Tanaka

  • Finally have installed the TMS-VIS.

Next plan

  • Detach white tapes and release the cables.
  • Connect the cables to flanges.
  • Configure the digital models properly.
    • Engage the logical channels and the assigned physical channels.
  • Check the signal integrity
    • To do so, the hanged table should move slightly.
    • But never jump to it, as we need to install the BRT on TMS-VIS; we need rather a rigid stage when we torque screws to fix BRT to TMS-VIS.
    • So, Uraguchi-san suggested the procedure. It should be docuented later. It is a little bit complicated about the dummy weights and restraints and new shims.
  • Install BRT on TMS-VIS.
  • Clean the sides of the optics to be installed into the vacuum chamber. (Ethanol+Acetone wiping with vectra alpha, then First Contact.) See here.

Wanted!

  • Tester!! lend from DGS or PEM??
  • M8 eyebolts for managing the dummy weight plates...
  • First contact to clean the side diameter of the optics.
  • Need a signal generator for LVDTs

KAGRA/Subgroups/AOS/TMSX_O3/2018-09-26 (last edited 2018-09-27 01:08:56 by TomotadaAkutsu)