* Installed optics for green path from GBS1, except for green QPD boards (See [[JGW-T1808962|https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8962]] for optical layout) | * Installed optics for green path from GBS1, except for green QPD boards (See [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8962|JGW-T1808962]] for optical layout) |
Line 11: | Line 11: |
* Other things * Height of Gig-E camera is a bit short * LVDT |
20181006
Today's activities
Workers: Akutsu, Michimura, K. Tanaka
GPT part installation
Installed optics for green path from GBS1, except for green QPD boards (See JGW-T1808962 for optical layout)
- we marked screw holes on optical table every 10 holes
- the position of GST2 was 25mm too far from GLNS1, so we moved it to the default position
- Other things
- Height of Gig-E camera is a bit short
- LVDT
Next Plan
- Install QPD boards and do the final cabling
- Check why Gig-E camera is not working
Wanted!
- M4-12mm (or longer) screws instead of M4-10mm for fixing mirror holders to 20mm dia. posts
- Spacer for Gig-E camera (height is shorter than 4-inch right now)