2073
Comment:
|
2114
|
Deletions are marked like this. | Additions are marked like this. |
Line 31: | Line 31: |
* [[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=73663|LIGO-D1101992]] | * [[https://dcc.ligo.org/cgi-bin/DocDB/ShowDocument?docid=73663|LIGO-D1101992 (public): LSC VAC ENCLOSURE - TOP ASSEMBLY aLIGO]] |
Vacuum Enclosure & Wiring for In-Vac PDs
Some of the core PDs and QPDs have to be placed inside the vacuum. Those PDs will be put in hermetic enclosures. The wires used to communicate with those PDs have to be also vacuum compatible. The tasks are: * Design the airtight enclosures * Make sure that the heat can escape from the PD. * Chose appropriate (vacuum compatible) wires for signal and power transmission.
具体的な目標
近場では、12月中旬のプロトタイプ納品を目指す。
Action Items
A/I化できたもの、されたもののリスト
AI_MIF_INVACPD# |
Identified on |
Assigned to |
Outcome |
Description |
001 仕様の確認 |
20120925 |
Akutsu |
|
設計上のdetailをLIGOに確認。どこで真空シールしてるのか?など。 |
002 プロトタイプ製作手段の確保 |
20120925 |
Akutsu |
|
NAOJ-ATC/MEかどこかにプロトタイプ製作をかけあう。予算はKAGRAから(?)。 |
003 プロトタイプ図面作成の指示、レビュー |
20120925 |
Akutsu |
|
回路上のPDの位置やレギュレータ、コネクタの位置によって外箱にあける穴の位置がかわるように見えるので、そのdetailを反映したプロトタイプ図面を、製作してもらうところにつくってもらう→みんなでレビュー |
004 プロトタイプ発注作業 |
20120925 |
Akutsu |
|
プロトタイプの発注作業 |
LIGO Link(s)