Differences between revisions 19 and 21 (spanning 2 versions)
Revision 19 as of 2012-09-28 02:05:17
Size: 2073
Comment:
Revision 21 as of 2012-09-28 02:10:33
Size: 2114
Comment:
Deletions are marked like this. Additions are marked like this.
Line 31: Line 31:
 * [[https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=73663|LIGO-D1101992]]  * [[https://dcc.ligo.org/cgi-bin/DocDB/ShowDocument?docid=73663|LIGO-D1101992 (public): LSC VAC ENCLOSURE - TOP ASSEMBLY aLIGO]]

Vacuum Enclosure & Wiring for In-Vac PDs

back to MIF task list

link to MIF meetings

Some of the core PDs and QPDs have to be placed inside the vacuum. Those PDs will be put in hermetic enclosures. The wires used to communicate with those PDs have to be also vacuum compatible.

The tasks are:

 * Design the airtight enclosures
 * Make sure that the heat can escape from the PD.
 * Chose appropriate (vacuum compatible) wires for signal and power transmission.

具体的な目標

近場では、12月中旬のプロトタイプ納品を目指す。

Action Items

A/I化できたもの、されたもののリスト

AI_MIF_INVACPD#

Identified on

Assigned to

Outcome

Description

001 仕様の確認

20120925

Akutsu

設計上のdetailをLIGOに確認。どこで真空シールしてるのか?など。

002 プロトタイプ製作手段の確保

20120925

Akutsu

NAOJ-ATC/MEかどこかにプロトタイプ製作をかけあう。予算はKAGRAから(?)。

003 プロトタイプ図面作成の指示、レビュー

20120925

Akutsu

回路上のPDの位置やレギュレータ、コネクタの位置によって外箱にあける穴の位置がかわるように見えるので、そのdetailを反映したプロトタイプ図面を、製作してもらうところにつくってもらう→みんなでレビュー

004 プロトタイプ発注作業

20120925

Akutsu

プロトタイプの発注作業

LIGO Link(s)

KAGRA/Subgroups/MIF/PDVac (last edited 2012-11-19 23:04:06 by TomotadaAkutsu)