Line 2: Line 2:
 * 2022/10/21(Fri) 17:00-  * 2022/10/28(Fri) 17:00-
Line 40: Line 40:
  * JPS meeting
   * Online
   * Registration will start 15th Nov.
Line 56: Line 60:
  * 10/18,19 YokozaWashimi (Niigata)
Line 65: Line 68:
   * OMC : In air
   * TMSY : In vac, test today(?)
  * Opened the gate valves between PRM and PR3
   * OMC : In air, finalize will be performed early Nov.
   * TMSY : In vac, leak test done
  * Opened the gate valves between IMC and IMM
Line 70: Line 73:
  * FPMI lock succeeded!   * Initial alignment experiment
   * 16:00- everyday

  * PRMI lock trial
   * Search the good alignment

  * FPMI lock succeeded
Line 85: Line 94:
   * TMSY pumping down started
Line 91: Line 99:
   * Control loop done
Line 94: Line 103:
   * WFS settings, optics optimization
   * Beam profile
measurements
   * Sensing matrix measurements
Line 123: Line 131:
 * Barometers and infrasound placement underground
  * Set the temperature, humidity and barometer to each station
Line 133: Line 138:
  * Prepared the new mini rack
Line 134: Line 140:
  * Magnetic injection   * Magnetic injection (After Washimi-san visiting to Virgo)
Line 136: Line 142:

 * Voltmeter preparation
  * Detail by Kiyota-san
  * Model and channel name update

 * Schumann resonance outside
  * Measured from end of Aug.
  * Prepared the AC power supply and LAN cable(Today?)
Line 176: Line 190:
  * Report of Niigata visiting   * Virgo visitting plan
Line 179: Line 193:
  * Investigating the MN oplev glitch   * Report of the VK PEM meeting

Weekly PEM meeting

General announcement

  • KAGRA visiting plan
    • Welcome to visit KAGRA site
    • Please contact to Ohashi-san
  • Important discussion with ET people
    • Magnetic field from infrastructure
    • If you want to join the discussion, please let Yokozawa know.
  • Visiting to Virgo site
    • By C2C budget
    • Contact to Virgo people
      • Next year?
    • Washimi will visit Virgo in mid. Nov (NAOJ budget)

Meeting and Conference issue

  • 第3回新学術「地下宇宙」若手研究会@つくば国際会議場
  • 第8回極低放射能技術研究@筑波大学
    • 2022年11月24日(木)~26日(土)
  • ET annual meeting @ EGO
    • Nov.15-17
  • The 30th KAGRA Face-to-Face meeting in hybrid style
    • Nov 30-Dec 1, 2022 JST
    • url

    • registration page (Nov. 11th)

    • Please have a presentation for master thesis
  • JPS meeting
    • Online
    • Registration will start 15th Nov.
  • GR23 in Beijin, China
  • GWPAW2022 in Melbourne Australia
  • GRASS 2022 in Padova, Italy
  • Other meetings url

If you have some presentation about PEM related, please contact to me.

Business travel

  • Depending on the situation of COVID-19
  • To Kamioka
    • 10/16 - 10/26 Kiyota(OMU)
    • 10/19 - 10/29 Miyamoto(ICRR)
    • 10/23 - 10/29 Fukunaga(OMU)
  • From Kamioka
    • Washimi go to Itary
      • 11/8 : Gran Sasso (GSSI, LNGS)
      • 11/10~19 : Virgo

General issue

  • Overall schedule
    • All leak test at center area was performed
      • OMC : In air, finalize will be performed early Nov.
      • TMSY : In vac, leak test done
    • Opened the gate valves between IMC and IMM
  • Interferometer overall
    • Initial alignment experiment
      • 16:00- everyday
    • PRMI lock trial
      • Search the good alignment
    • FPMI lock succeeded
      • DARM(AS17), CARM(REFL45), MICH(REFL51->POP17)

      • Latest sensitivity klog22097

      • Calibration evaluation
      • Control filter optimization
      • Interferometer characterization
    • X arm commissioning
      • End X IM 81K
      • We will start the noise budget of the new oplev again
      • OMC ASC using the Xend test mass
        • Signal was detected in OMC PD
    • Y arm commissioning
      • IY duct shield cooling
    • New high power laser
      • PMC locked
    • ISS
      • Control loop done
      • Characterization is ongoing
    • ASC preparation
      • Sensing matrix measurements
  • Schedule
  • PEM schedule
    • Re-installation of PEMs toward O4
  • 出張PEM injection (planning form)

Jurnal paper issue

Details are here!

Preparation for O4

  • Weather station
    • Weather in KAGRA entrance
    • New weather station
    • Calibration
  • Investigation of the PEM injection is just started
    • New DAC preparation
    • Prepared the new mini rack
    • Acoustic injection at PSL/IMMCS/X/Y-end
    • Magnetic injection (After Washimi-san visiting to Virgo)
    • Portable PEM injectors
  • Voltmeter preparation
    • Detail by Kiyota-san
    • Model and channel name update
  • Schumann resonance outside
    • Measured from end of Aug.
    • Prepared the AC power supply and LAN cable(Today?)
  • After O4
    • RF monitor with mokugo
    • Tiltmeter
    • RI detector
    • Newtonian noise
  • Discussion with DET members
    • Daily summary page PEM

Progress report

  • Yuzurihara
    • Pastavi
    • Data Quality Report slide

    • Data quality evaluation
  • Suzuki
    • Water simulation
  • Hoshino
    • Seismic motion analysis
  • Miyamoto
    • Weather analysis
  • Kume
    • Report of paper progress
  • Fukunaga
    • Schumann resonance
  • Kiyota
    • Power line noise investigation
  • Nishizawa
    • Water newtonian noise
    • Magnetic field analysis
  • Washimi
    • Virgo visitting plan
  • Yokozawa
    • Report of the VK PEM meeting

Place for memo