== iKAGRA ETM suspension preparation log == === 1. Schedule === * 12th Jan- (2 weeks) Disassembling, Washing, and transportation * 25th Jan - (2 weeks) Assembling and Test Hanging with an Al dummy mirror * 7th Feb- (1 week) coil winding, measurement of transfer function, transportation to the End area and installation test * 15th Feb- (1 week)installation<
> Suspensions and mirrors were installed on 17th Feb so this 6 weeks task was completed on schedule. === 2. Disassembling in the ATC clean booth at Mitaka (12th-19th Jan.) === * One suspensions was moved from the desiccator at the west end of TAMA and the other was moved from the vacuum tank. * Two nuts stuck. Hirata-san removed them. * A Cu screw stuck. Hirata-san removed it. === 3. Washing and transportation to Kamioka === [Hirata-san] * The ultra sonic washer at ATC was broken on 20th Jan. <
> A new washer was ordered on 22th(Fri) and arrived at Mitaka on 25th(Mon). * Eight screws for adjusting the IM holding plate was dirty.<
> Takahashi-san ordered similar screws. === 4. New parts preparation === ==== 4.1 Coil bobbin (Delivered to Kamioka on 4th Feb.) ==== [Takahashi-san, Tatsumi-san] [[http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0047/T1604741/001/Coil_Preparation_2016.pdf|coil bobbin]] * The outer diameter of the coil has been changed from 14.2mm to 14.5mm. * Due to this change, the number of winding becomes 39 from 41. * Wind 13 times / 1 layer. ==== 4.2 Coil winding (8th-16th Feb.) ==== [Kuwahara-san, and Ushiba-san from U-Tokyo, Lee-san from Okazaki, and Ohishi] * We used coil winding machine. * Lead wires from the bobbin to Dsub connector were too short (20cm). The length must be 40cm or more. * At the end of the lead wires, D-sub pins are swaged. We have run short of pins and waiting for delivery on 29th Feb(Mon). * Peeling off the coating of wires longer than the length of those pins make the wire broken easily. ==== 4.3 D-sub connector plates (8th Feb.) ==== [Takahashi-san]  [[attachment:D-sub_connector_plate.pdf|{{attachment:D-sub_connector_plate.pdf||width=600}}]]<
> * M3 holes were changed to phi3.1 holes. Yamamoto-san used drilling machine at Kamioka surface office. * One must be careful about the pillar position in order to attach this plate to the suspension. ==== 4.4 15pin-9pin changer for coil driver output [Ushiba-san, Ohishi] ==== ==== 4.5 Screws in replace with Cu screws [Ohishi] ==== * Replaced all Cu screws to stainless screws. Magnetism problem was indicated. ==== 4.6 D-sub 9pin - BNC changer [Doi-san] ==== * Used to input the signal from the laser displacement measurement system to AA/ADC of the digital system. === 5. Jigs === ==== 5.1 Magnet and standoff fixture jig ==== * We used ==== 5.2 Dock (mirror hanging jig) ==== (4 ; with the diameter of 2mm and the length of 5mm NdFeB magnets) [Tomaru-san, Yamamoto-san] === 6. Some other items === ==== 6.1 Pico-motors and PZTs ==== We have 4 pico-motors except for x-axis (the direction of the light ) y, z, pitch, yaw ==== 6.2 Coil drivers ==== We use KAGRA coil driver; we need to cheek its performance. ==== 6.3 Cables ==== ==== 6.4 Mirrors ==== Two TAMA PRM mirrors (with about 50% and 90% reflectivities each, resultant contrast becomes 96%) were delivered to Kamioka on 12th Feb. ==== 6.5 Mirror container [Tatsumi-san] ==== [[attachment:MirrorContainer.pdf|{{attachment:MirrorContainer.pdf||width=600}}]]<
> * Some plates once used for transportation of MC mirrors were used * Two places of the container were cut to avoid standoffs. ==== 6.6 Stages ==== * Condensation * Vacuum compatibility? === 7. Assembling === [Tomaru-san, Ohishi, Yamamoto-san] <
> On 21th, suspension frame, security frame, xy stages completed === 8. Hanging === [Yamamoto-san, Uchiyama-san, Doi-san, and Ohishi] <
> Hanging jig preparation === 9. Transfer Function Measurement (8th-16th Feb.) === [Shoda-san, Hayama-san, Ushiba-san, Kuwahara-san, Kokeyama-san, Kuwahara-san, Tomaru-san, Lee-san, and Ohishi] * First Shoda-san kindly made a simple model under PR2 digital system for this test. * === 10. Preparation of End area and suspension transportation to the End === [Kimura-san, Sawada-san, Tomaru-san, Prof. Suzuki, Telada-san, Uchiyam-san] * Uchiyama-san bought many things we need at the end area and KEK member transported them and cleaned the work area. === 11. Installation [Akutsu-san, Uchiyama-san, Yamamoto-san, Miyoki-san, and Ohishi ] (15th-17th Feb.) === ==== 11.1 Suspension installation ==== *Suspension was installed by Miyoki-san, Akutsu-san and Yamamoto-san on 15th Feb at the Yend. *Suspension and mirrors were installed by at the Xend. * ==== 11.2 Mirror installation ====