= Type-A Meeting on 2016/7/5 =
2016/7/5 13:00 - 14:00 @Kamioka

Participants: Takahashi, Ishizaki, Sato, Okutomi

=== Minutes ===
 0-2 Simulation (Okutomi)
  * The frequency shift might be due to damping model.
  * Matlab model was remade.
  * Sensors and actuators were added to the BF stage.
 1-1 Clean Booth (FCL)
  * The booth will be ready in December.
 2-1 Setting of top chamber (VAC)
  * The schedule was shifted to December.
 2-3 Setting of cross chamber (VAC)
  * From 8th July, presence on 11th.
 3-2 Assembly of TF+IP (Sato)
  * The place should be considered again.
 3-5 ACC preparation (Sato)
  * 5 sets of ACC were measured.
 5-1 Manufacturing of blade (Takahashi)
  * Cutting of 12 blades was finished.
 5-2 Assembly of BF (Hirata)
  * Will be started in September.
 6-3 Test of prototype (Ishizaki)
  * The first setup and its procedure were shown.
  * Thin dummy weight and short hoock should be prepared.
  * Some cap screws on stop plates should be replaced to stop screws.
 6-4 Design of release sensor (Sato)
  * Under cable connection.
 8-1 Design of dummy payload (Okutomi, Ishizaki)
  * Interferometer test was canceld.
  * The EQ stop and the dummy payload should be ordered together in August.
 9-2 Transportation to 2F (Takahashi, Ishizaki)
  * Situation of the Y-end was investigated.
  * Maximum box width, which can go through the tunnel, was 1.5m.
  * Access road from Mozumi entrance was improved.
 9-3 Cable assembly (Sato)
  * Ask CRY number of cables.

Next meeting: 2016/7/19 13:00

Task list

http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4792

Type-A Meeting on 2016/7/5

2016/7/5 13:00 - 14:00 @Kamioka

Participants: Takahashi, Ishizaki, Sato, Okutomi

Minutes

  • 0-2 Simulation (Okutomi)
    • The frequency shift might be due to damping model.
    • Matlab model was remade.
    • Sensors and actuators were added to the BF stage.
    1-1 Clean Booth (FCL)
    • The booth will be ready in December.
    2-1 Setting of top chamber (VAC)
    • The schedule was shifted to December.
    2-3 Setting of cross chamber (VAC)
    • From 8th July, presence on 11th.
    3-2 Assembly of TF+IP (Sato)
    • The place should be considered again.
    3-5 ACC preparation (Sato)
    • 5 sets of ACC were measured.
    5-1 Manufacturing of blade (Takahashi)
    • Cutting of 12 blades was finished.
    5-2 Assembly of BF (Hirata)
    • Will be started in September.
    6-3 Test of prototype (Ishizaki)
    • The first setup and its procedure were shown.
    • Thin dummy weight and short hoock should be prepared.
    • Some cap screws on stop plates should be replaced to stop screws.
    6-4 Design of release sensor (Sato)
    • Under cable connection.
    8-1 Design of dummy payload (Okutomi, Ishizaki)
    • Interferometer test was canceld.
    • The EQ stop and the dummy payload should be ordered together in August.
    9-2 Transportation to 2F (Takahashi, Ishizaki)
    • Situation of the Y-end was investigated.
    • Maximum box width, which can go through the tunnel, was 1.5m.
    • Access road from Mozumi entrance was improved.
    9-3 Cable assembly (Sato)
    • Ask CRY number of cables.

Next meeting: 2016/7/19 13:00

Type-A Meeting on 2016/6/28

2016/6/28 13:00 - 14:30 @The 4th meeting room

Participants: Takahashi, Ishizaki, Sato, Okutomi

Minutes

  • 0-1 Assembly model (Ishizaki)
    • Made the test setup.
    0-2 Simulation (Okutomi)
    • No progress. The results will be reported in the next VIS meeting.
    1-1 Clean Booth (FCL)
    • Present design: The booth is hung from the ceiling.
    2-3 Setting of cross chamber (VAC)
    • From 8th July, presence on 11th.
    3-5 ACC preparation (Sato)
    • Working space: The 20m lab was arranged on 27th.
    4-3 Standard filter (Hirata)
    • Assembly of FR and measurement: 1 set was finished.
    5-1 Manufacturing of blade (Takahashi)
    • Cutting: 6 blades by July + 6 blades by Sep.
    5-6 Design of damper (Sato)
    • Device: It is difficult to put the devices at the center of suspension point.
    6-1 Design of EQ stop (Ishizaki)
    • Modeling: 3D model for the test setup was built.
    6-3 Test of prototype
    • Frame lock, extension rods, adjusters were delivered.
    • Hoist's tool will be necessary.
    • Test items related to the frame design have high priority. Target date is 22th July.
    6-4 Design of release sensor (Sato)
    • Bases and shims were delivered.
    • Plate additional machining: Delivery on 29th.
    • Circuit: LED box was made. Cabling has not been applied yet.
    8-1 Design of dummy payload (Okutomi, Ishizaki)
    • Cartoon: Okutomi should send to Ishizaki soon!
    9-1 Establishment of procedure (Takahashi, Okutomi)
    • Test plan is made parallel with test work. Check the list of test items.
    9-2 Transportation to 2F (Takahashi, Ishizaki)
    • Situation of the site will be checked in 5-7th July.
    • Electric crawler is limitted, for example, for 200kg load.
    9-3 Cable assembly (Sato)
    • Number of cables: CRY will decide it by the end of June.

Next meeting: 2016/7/5 13:00

Type-A Meeting on 2016/6/21

2016/6/21 13:00 - 14:00 by Skype

Participants: Takahashi, Ishizaki, Sato

Minutes

  • 0-1 Assembly model (Ishizaki)
    • Made the test setup.
    0-2 Simulation (Okutomi)
    • Deadline: The end of June
    2-3 Setting of cross chamber (VAC)
    • Work: From 8th July, presence on 11th.
    3-5 ACC preparation (Sato)
    • Make working space in the 20m lab on 27th June.
    4-3 Standard filter (Hirata)
    • Assembly of FR and measurement: by August for 6 sets.
    4-5 Procurement of magnets (Takahashi)
    • Size: 13mm, 72PSC for each
    5-1 Manufacturing of blade (Takahashi)
    • Cutting: 6 blades by July + 6 blades by Sep.
    5-6 Design of damper (Sato)
    • Device: The last one was too small, actually about 125mm. Design for vertical as well.
    6-1 Design of EQ stop (Ishizaki)
    • Modeling: 3D model for the test setup was build.
    6-3 Test of prototype
    • Frame lock: Delivered by 24th.
    • Other parts (rod, adjuster, bolts) will be ordered.
    6-4 Design of release sensor (Sato)
    • Base: Making in ATC.
    • Plate additional machining: Ordered.
    • Circuit: LED will be tested.
    8-1 Design of dummy payload (Okutomi, Ishizaki)
    • Cartoon: Okutomi should send to Ishizaki soon!
    • Mirror holder: Refer the mirror box for PR.
    9-1 Establishment of procedure (Takahashi, Okutomi)
    • Test plan: Check FR for 2 BFs.
    9-3 Cable assembly
    • Number of cables: Thermocouples are added. Ask Tomaru total number.

Next meeting: 2016/6/28 13:00

Type-A Meeting on 2016/6/14

2016/6/14 13:00 - 15:00 @ Room 210

Participants: Takahashi, Ishizaki, Sato, Okutomi

Minutes

  • 0-1 Assembly model (Ishizaki)
    • Step: From EQ stop, next with chamber.
    0-2 Simulation (Okutomi)
    • Problem: Conversion to Simulink was ok. The structure of control has a problem in Matlab. Reconstructing now.
    3-5 ACC preparation (Sato)
    • Space: Make working space in the 20m lab.
    5-1 Manufacturing of blade (Takahashi)
    • Design: 5 blades are used for 200kg load.
    5-6 Design of damper (Sato)
    • Device: Asking design of LVDT-Act. to VIRGO. The device is located at the center of mass.
    6-1 Design of EQ stop (Ishizaki)
    • Structure analysis: Two cases were calculated. Share stress was 1/6 of limit, and principal stress was 1/7 of limit respectively in the maximum case.
    • Modeling: Making with consideration of procedure and tools.
    • Frame lock: Maximum stress was 160MPa with thickness of 30mm (limit 180MPa).
    6-4 Design of release sensor (Sato)
    • Position: Inner side of the stage. Need to addtional machining to the EQ stop plate.
    • Electronics: Circuit is simple in the test (handmade).
    8-1 Design of dummy payload (Okutomi, Ishizaki)
    • Condition: 25cm mirror, alignment by moving mass. Make a cartoon.
    • Actuation: Length control is necessary? Check PZT actuator.
    9-1 Establishment of procedure (Takahashi, Okutomi)
    • Test plan: Prepare for 2 sets of release sensors. Check FR for 2 BFs.

Next meeting: 2016/6/21 13:00