Line 6: Line 6:
  * Fabian took photos of the cleanroom in the ATC to help decide whether it is a good place to assemble PIs for Type A/B.
  * Hirata-san ordered and received wire for the BS and RM (will be cleaned 7/19).
  * Hirata-san received remachined locking parts for the IM (will be cleaned 7/19).
  * Hirata-san ordered additional Misumi parts to be used with the IM locking parts.
  * Fabian and Hirata-san weighed the masses that they've been constructing in the cleanroom and found a 600 g discrepancy from the Inventor (too light) for the IM. Although the density assumed in the Inventor agrees with spec sheet values, it doesn't match the parts. Adjusting the density to match a few key parts reduces the discrepancy to 60 g. More investigation is planned.
  * Hirata-san ordered a medium-capacity scale to weigh the individual parts more precisely and help locate the discrepancy.
  * Hirata-san organized to do a fit/function test of the BS winches and training session with Ikenoue-san of ATC on 7/25.
  * Hirose-san and his team successfully removed the misglued prisms from the dummy BS.
  * Fabian travelled to Kashiwa and removed most of the glue from the face of the dummy BS (where the flags had been). There is still some adhesive remaining on both the face and barrel, which will require more work in a second trip.
  * Shoda-san took a suitable segment of geophone noise data for analysis. Fabian will track down the calibration factors.
  * Hirata-san worked on 2D drawings for the PI cable clamps and the magnetic damper for the lower breadboard.
  * Hirata-san worked on the 3D assembly for SR2.
  * Mark and Fabian went to Kashiwa to clean up glue residue on the dummy BS and do a fit/function test of Tatsumi-san's modified tooling.
   * Most of the remaining glue came off with soaking in acetone, but there is still some in the machining grooves in the Al surface. Probably more work is required.
   * A set of cleanroom shoes borrowed from the ATC disintegrated when worn (the plastic had perished from age), which put small pieces of foam all over the floor in Hirose-san's cleanroom and required a lot of clean-up with a sticky roller! Cleanroom suits and shoes for use by Type B team at Mitaka/Kashiwa have been ordered, but will take another week to arrive.
   * The flag holding parts are now much easier to place and remove, much reducing the risk of breaking flags after gluing.
   * The sapphire and metal prisms from both the first BS gluing and the PR3 hanging test mirror were brought back to Mitaka for ultrasonic cleaning to remove glue, so they can be reused.
  * Hirata-san found the SR versions of the screws for immobilizing the IM and IRM. These fit much better than the BS ones (despite being the same design) and will be used for the BS.
Line 20: Line 14:
   * Akutsu-san is working to get wide-mouth OSEMs    * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8)
Line 30: Line 24:
  * Apply grease to jacks for assembly frame (Takahashi) - DONE
  * Finish assembly of BS IM, RM and IRM (Fabian) - DONE
Line 36: Line 28:
  * Remove prism from dummy BS (Hirose, Fabian?) - DONE
Line 38: Line 29:
  * Buy wire for BS and RM (Hirata) - DONE
  * Clean wire for BS and RM (Hirata) - 7/19
  * Do fit/function test of winches (Fabian/Hirata) - ORGANIZED for 7/25
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
Line 43: Line 34:
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - just started.   * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark and Fabian went to Kashiwa to clean up glue residue on the dummy BS and do a fit/function test of Tatsumi-san's modified tooling.
      • Most of the remaining glue came off with soaking in acetone, but there is still some in the machining grooves in the Al surface. Probably more work is required.
      • A set of cleanroom shoes borrowed from the ATC disintegrated when worn (the plastic had perished from age), which put small pieces of foam all over the floor in Hirose-san's cleanroom and required a lot of clean-up with a sticky roller! Cleanroom suits and shoes for use by Type B team at Mitaka/Kashiwa have been ordered, but will take another week to arrive.
      • The flag holding parts are now much easier to place and remove, much reducing the risk of breaking flags after gluing.
      • The sapphire and metal prisms from both the first BS gluing and the PR3 hanging test mirror were brought back to Mitaka for ultrasonic cleaning to remove glue, so they can be reused.
    • Hirata-san found the SR versions of the screws for immobilizing the IM and IRM. These fit much better than the BS ones (despite being the same design) and will be used for the BS.
  • Type B ongoing issues
    • OSEMs
      • Akutsu-san is working to get wide-mouth OSEMs (2 assembled; first 4 expected to be assembled and washed by 8/8)

    • Longer cables for BF->PI and SF->PI.

      • Connectors RECEIVED, cables being made.
    • SR machining test ongoing.
    • Lower breadboard stuff
      • Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
      • Breadboard springs (in manufacture, expected end of July)
    • Documents
  • To-do list during Mark's vacation
    • Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
    • Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
    • Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
    • Remove glue from dummy BS face (Fabian) - partly done.
    • Reglue flags and prisms (Tatsumi, Fabian)
    • Clean wire for BS and RM (Hirata) - DONE
    • Get new winch parts for new wire diameters - design received from Ikenoue-san
    • Do fit/function test of winches (Fabian/Hirata)
    • Ship winches to Kamioka (Hirata/Fabian)
    • Work on BS simulation (Fabian)
    • Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
    • Write more of payload assembly procedure (Fabian)
    • Write more of main assembly procedure (Mark)
  • Longer term to-do list
    • Do BS Simulink model (Mark, Kokeyama)
    • Do 2D drawings of SR2 parts (Hirata)
    • Redesign SRx IM wire clamps for larger prisms, remachined RMs.
    • Order SRM/PRM parts (Hirata/Shoda)
    • Order SRx fasteners (Hirata)
    • Check SR RM machining test progress (Hirata)